10-Inch Crude Oil Pipeline - Billings, Dunn, Stark
From the ProvenHand pipeline wiki
10-Inch Crude Oil Pipeline - Billings, Dunn, Stark is a crude oil pipeline in North Dakota, operated by Belle Fourche Pipeline Co. Construction began in 2015. It runs 20 miles of 10" pipe.
| 10-Inch Crude Oil Pipeline - Billings, Dunn, Stark | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Project type | New build[2] |
| Status | In service[3] |
| Commodity | Crude oil[2] |
| Owner and operator | |
| State | North Dakota[1] |
| Counties | Billings, Dunn, Stark[2] |
| Approved | 10 July 2014[2] |
| Construction started | January 2015[4] |
| North Dakota PSC case | PU-14-135[1] |
| Contractors | |
| Technical information | |
| Length | 20 mi[2] |
| Pipe size | 10"[2] |
| Cost | anticipated cost of the Project is approximately $7.9 million[2] |
| On ProvenHand | |
| Hands listed | 0 |
10-Inch Crude Oil Pipeline - Billings, Dunn, Stark is a crude oil pipeline in North Dakota, operated by Belle Fourche Pipeline Co. Construction began in 2015. It runs 20 miles of 10" pipe.
Contractorsedit
| Contractor | Work |
|---|---|
| Frontier Services[5] | Prime |
| Keitu Engineers & Consultants[5] | project management (listed as project manager in the pre-construction minutes) |
Inspection
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on 10-Inch Crude Oil Pipeline - Billings, Dunn, Stark? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “North Dakota Public Service Commission: case search (pipeline siting)”. North Dakota Public Service Commission. Retrieved 3 October 2026.
- “Findings of Fact, Conclusions of Law and Order, Case No. PU-14-135 (Belle Fourche 10-inch crude oil pipeline)”. North Dakota Public Service Commission. 10 July 2014. Retrieved 3 October 2026.
- “Permit Compliance Final Inspection Report, 10-inch crude oil pipeline, PU-14-135”. Houston Engineering, Inc. (filed with the North Dakota Public Service Commission). 31 August 2016. Retrieved 3 October 2026.
- “Weekly construction report, week ending 2015-01-31, Skunk Hill to Dickinson 10-inch, PU-14-135”. Belle Fourche Pipeline Company (filed with the North Dakota Public Service Commission). 3 February 2015. Retrieved 3 October 2026.
- “Pre-construction conference minutes (held 2015-01-14), Belle Fourche 10-inch crude pipeline, PU-14-135”. Belle Fourche Pipeline Company (filed with the North Dakota Public Service Commission). 6 October 2015. Retrieved 3 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.