Apex Expansion Project is a natural gas pipeline in Nevada, Utah and Wyoming, operated by Kern River Gas Transmission Company. It runs 28 miles of 36" pipe.
| Apex Expansion Project | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Project type | Expansion[2][3] or Loop[4][sources disagree] |
| Status | In service[2] |
| Commodity | Natural gas[2] |
| Owner and operator | |
| Facility project | |
| States | Nevada, Utah, Wyoming[1][2] |
| Counties | Nevada: Clark Utah: Beaver, Davis, Millard, Morgan, Salt Lake, Utah Wyoming: Uinta[4] |
| Approved | 16 September 2010[1] |
| In service | October 2011[2] or 1 October 2011[5][sources disagree] |
| FERC docket | CP10-14[1] |
| FERC pre-filing docket | PF09-7[1] |
| Contractors | |
| Technical information | |
| Length | 28 mi[1][2] |
| Pipe size | 36"[2] |
| Capacity | 266 MMcf/d (FERC project list)[1][2] |
| Horsepower added | 78,000 hp[4] |
| Cost | $30 million (EIA estimate; no dollar year given)[2] or $373.4 million (estimated project capital cost stated in the certificate order)[4][sources disagree] |
| On ProvenHand | |
| Hands listed | 0 |
Apex Expansion Project is a natural gas pipeline in Nevada, Utah and Wyoming, operated by Kern River Gas Transmission Company. It runs 28 miles of 36" pipe.
Contractorsedit
| Contractor | Work | Scope |
|---|---|---|
| Barnard Pipeline, Inc.[6] | Prime | Built 28 miles of high-pressure natural gas pipeline through the Wasatch Range, Utah (the site's 2011 milestone, called the Wasatch Loop Pipeline), with grades of 40 percent or steeper and helicopter delivery of crews and materials |
| Milbar Hydro-Test, Inc.[7] | Hydrotest | Pre-cleaning, filling, hydrotesting, air testing, caliper pig run and dew point drying: 28 miles of 36-inch |
Sources disagree
These sources give different values for the same fact. Each value is listed with the sources that give it.
| Fact | Values given |
|---|---|
| Project type | |
| Cost | |
| In service |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Apex Expansion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
- “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
- “FERC eLibrary docket CP10-14”. Federal Energy Regulatory Commission. 2 November 2009. Retrieved 3 October 2026.
- “Order Issuing Certificate, Kern River Gas Transmission Company, Apex Expansion Project (CP10-14)”. Federal Energy Regulatory Commission. 16 September 2010. Retrieved 4 October 2026.
- “Notice of Placement In Service of Apex Expansion Facilities (CP10-14)”. Kern River Gas Transmission Company (filed with FERC). 5 October 2011. Retrieved 4 October 2026.
- “Our Story (milestones)”. Barnard Construction Company, Inc. Retrieved 3 October 2026.
- “Kern River - APEX Expansion (project page)”. Milbar Hydro-Test, Inc. Retrieved 3 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.