Cheyenne Compressor Station Expansion Project is a natural gas pipeline expansion in Colorado and Wyoming, operated by Wyoming Interstate Gas Co. It entered service in 2018.

Cheyenne Compressor Station Expansion Project
Also calledWIC Cheyenne Compressor Station Expansion Project[1]
General information
KindPipeline project[2] or Facility project[3][sources disagree]
Project typeExpansion[1][2]
StatusIn service[2]
CommodityNatural gas[2]
Operator
Owner and operator
StatesColorado, Wyoming[2][3]
CountiesWeld[3][4]
In service23 May 2018[2]
FERC docketCP18-117[2]
Technical information
Pipe size36"[5]
Capacity222 MMcf/d additional capacity (EIA)[2]
Capacity addedabout 222,000 Dth/d of firm transportation service from the Flying Hawk Interconnect[5] or an additional 220,000 dekatherm per day of capacity from its receipt at the Flying Hawk Interconnect[4][sources disagree]
Cost$2.169 million (EIA estimate; no dollar year given)[2] or $2,168,916[5][sources disagree]
On ProvenHand
Hands listed0

Cheyenne Compressor Station Expansion Project is a natural gas pipeline expansion in Colorado and Wyoming, operated by Wyoming Interstate Gas Co. It entered service in 2018.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Capacity added
  • about 222,000 Dth/d of firm transportation service from the Flying Hawk Interconnect[5]
  • an additional 220,000 dekatherm per day of capacity from its receipt at the Flying Hawk Interconnect[4]
Cost
  • $2.169 million (EIA estimate; no dollar year given)[2]
  • $2,168,916[5]
Kind
  • Pipeline project[2]
  • Facility project[3]

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Cheyenne Compressor Station Expansion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC eLibrary docket CP18-117”. Federal Energy Regulatory Commission. 15 March 2018. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “FERC notice of request under blanket authorization, Cheyenne Compressor Station Expansion Project (CP18-117)”. FERC. 23 March 2018. Retrieved 4 October 2026.
  4. “Notice of Request Under Blanket Authorization; Wyoming Interstate Company, LLC (Docket No. CP18-117-000), Federal Register 2018-06411”. Federal Energy Regulatory Commission (published in the Federal Register). 30 March 2018. Retrieved 4 October 2026.
  5. “Environmental Assessment Report, Cheyenne Compressor Station Expansion Project (CP18-117)”. FERC. 22 May 2018. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.