ETC Tiger Pipeline Expansion Project is a natural gas pipeline expansion in Louisiana, operated by ETC Tiger Pipeline, LLC. Construction began in 2011. It runs 20.5 miles of 42" pipe.

ETC Tiger Pipeline Expansion Project
Also calledETC Tiger Pipeline (Louisiana) Expansion[1]
General information
KindPipeline project[1]
Project typeExpansion[2][3]
StatusIn service[2]
CommodityNatural gas[2]
Owner and operator
StateLouisiana[1][2]
Approved3 February 2011[1]
Construction started9 March 2011[4]
In service19 July 2011[2] or 1 August 2011[5][sources disagree]
FERC docketCP10-459[1]
Technical information
Length20.5 mi[1][2][5]
Pipe size42"[2][5]
Capacity400 MMcf/d (FERC project list)[1][2]
Horsepower added30,565 hp[5]
Cost$193 million (EIA estimate; no dollar year given)[2] or $141,064,913 total forecasted spend based on actual costs through 2011-12-31 (filed Exhibit K cost $193,062,267)[6][sources disagree]
On ProvenHand
Hands listed0

ETC Tiger Pipeline Expansion Project is a natural gas pipeline expansion in Louisiana, operated by ETC Tiger Pipeline, LLC. Construction began in 2011. It runs 20.5 miles of 42" pipe.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Cost
  • $193 million (EIA estimate; no dollar year given)[2]
  • $141,064,913 total forecasted spend based on actual costs through 2011-12-31 (filed Exhibit K cost $193,062,267)[6]
In service
  • 19 July 2011[2]
  • 1 August 2011[5]

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on ETC Tiger Pipeline Expansion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “FERC eLibrary docket CP10-459”. Federal Energy Regulatory Commission. 15 June 2010. Retrieved 3 October 2026.
  4. “Notice of Commencement of Construction, ETC Tiger Pipeline Expansion Project, Phase I (CP10-459)”. ETC Tiger Pipeline, LLC (filed with FERC). 24 June 2011. Retrieved 4 October 2026.
  5. “Notice of Commencement of Service, ETC Tiger Pipeline Expansion Project, Phase I (CP10-459)”. ETC Tiger Pipeline, LLC (filed with FERC). 5 August 2011. Retrieved 4 October 2026.
  6. “Cost Statement Pursuant to Section 157.20(c)(3), ETC Tiger Pipeline Expansion Project (CP10-459)”. ETC Tiger Pipeline, LLC (filed with FERC). 1 February 2012. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.