Florida Gas Transmission East-West Project is a natural gas pipeline lateral in Louisiana and Texas, operated by Florida Gas Transmission Company, LLC. Construction began in 2018 and the line entered service in 2019. It runs 24.7 miles of 12" pipe.
| Florida Gas Transmission East-West Project | |
|---|---|
| Also called | East-West Project[1] |
| General information | |
| Kind | Pipeline project[2] |
| Project type | Lateral[1] |
| Status | In service[1] |
| Commodity | Natural gas[1] |
| Owner and operator | |
| Operator | |
| States | Louisiana, Texas[1][2] |
| Counties | Matagorda, Wharton[3] |
| Approved | 5 April 2018[2] |
| Construction started | 5 July 2018[4] |
| In service | 22 January 2019[1] |
| FERC docket | CP17-8[2] |
| Technical information | |
| Length | 24.7 mi[1][2] |
| Pipe size | 12"[3] |
| Capacity | 275 MMcf/d (FERC project list)[1][2] |
| Cost | $68.9 million (EIA estimate; no dollar year given)[1] |
| On ProvenHand | |
| Hands listed | 0 |
Florida Gas Transmission East-West Project is a natural gas pipeline lateral in Louisiana and Texas, operated by Florida Gas Transmission Company, LLC. Construction began in 2018 and the line entered service in 2019. It runs 24.7 miles of 12" pipe.
Inspection
| Firm | Scope |
|---|---|
| Tetra Tech, Inc.[5] | FERC's third-party contractor on the Commission's construction/environmental inspections |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Florida Gas Transmission East-West Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
- “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
- “Ongoing Projects: Construction Underway (Pipeline News, May 2017)”. Pipeline News. May 2017. Retrieved 3 October 2026.
- “Bi-Weekly Environmental Status Report No. 1, East-West Project (CP17-8)”. Florida Gas Transmission Company, LLC (filed with FERC). 20 July 2018. Retrieved 4 October 2026.
- “Construction Inspection Report, East-West Project (CP17-8)”. Federal Energy Regulatory Commission. 15 August 2018. Retrieved 4 October 2026.