Tetra Tech, Inc.
From the ProvenHand pipeline wiki
Tetra Tech, Inc. is a third-party inspection firm.
| Tetra Tech, Inc. | |
|---|---|
| General information | |
| Industry | |
| On ProvenHand | |
| Hands listed | 0 |
Tetra Tech, Inc. is a third-party inspection firm.
This company article is a stub. You can help ProvenHand by expanding it.
Projects
Inspection
| Project | Scope | Years | Project built |
|---|---|---|---|
| Cedar Vale Compressor Station Project[4] | 2026 | ||
| TTC Connector TTC Project[5] | 2026 | ||
| CP Express Pipeline[6] | Environmental compliance inspections for FERC staff | 2025 | |
| Henderson County Expansion Project[7] | 2024 | ||
| Three Rivers Interconnection Project[8] | 2024 | ||
| Venice Extension Project[2] | Environmental compliance inspections for FERC staff | 2023–2024 | |
| Wahpeton Expansion Project[1] | FERC contractor for post-certification compliance inspections, working under contract to FERC | from 1 May 2024 | 2024 |
| Florida Gas Transmission East-West Project[9] | FERC's third-party contractor on the Commission's construction/environmental inspections | 2018–2019 | |
| Gulf Connector Expansion[10][11] | Listed as FERC contractor staff on FERC field and construction inspections of the compressor station sites (2018 reports) | 2018–2019 | |
| Marshall County Mine Panel 18W Project[12] | FERC's third-party contractor on the Commission's construction/environmental inspections | 2018–2019 | |
| Millennium Pipeline Eastern System Upgrade[13][14] | Performed FERC construction inspections under contract to FERC (January and February 2018 reports) | 2017–2019 | |
| Access South/Adair Southwest/Lebanon Extension[15] | FERC's third-party contractor on the Commission's construction/environmental inspections | 2017–2018 | |
| Gulf Coast Expansion Project[16][17] | Performed FERC construction inspections of the compressor station and lateral under contract to FERC (March and April 2018 reports) | 2018 | |
| Lone Star Project[18][19] | Listed as FERC contractor staff on FERC construction inspections of Compressor Stations 3A and 11A (April and June 2018 reports) | 2018 | |
| Marshall County Mine Panel 17W Project[20] | FERC's third-party contractor on the Commission's construction/environmental inspections | 2017–2018 | |
| National Fuel Gas Supply Line YM28 and Line FM120 Modernization Project[21] | FERC's third-party contractor on the Commission's construction/environmental inspections | 2018 | |
| Paiute 2018 Expansion Project[22] | FERC's third-party contractor on the Commission's construction/environmental inspections | 2018 | |
| St. Charles Parish Expansion[23][24] | Performed FERC construction inspections under contract to FERC (March and August 2018 reports) | 2018 | |
| Transco to Charleston Project[25] | FERC's third-party contractor on the Commission's construction/environmental inspections | 2017–2018 | |
| Valley Expansion Project[26] | FERC's third-party contractor on the Commission's construction/environmental inspections | 2018 | |
| Wekiva Parkway Relocation Project[27] | FERC's third-party contractor on the Commission's construction/environmental inspections | 2018 | |
| Delaware River Pipeline Relocation Project[28] | FERC's third-party contractor on the Commission's construction/environmental inspections | 2017 | |
| Florida Gas Transmission 12-Inch St. Petersburg Lateral Relocation Project[3] | FERC Environmental Inspector, named in the cc line of the final weekly status report | 2016 | |
| Western Kentucky Lateral Project[29] | FERC third-party contractor for environmental compliance inspection (named in the operator's in-service request) | 2016 | |
| Bradley Lateral Project[30] | FERC's contractor for the restoration inspection of September 28, 2016 | 2015 | |
| H-312 Pipeline Project[31] | FERC's contractor for the restoration inspection of June 6, 2016 | 2015 | |
| Lawrence County Expansion Project[32] | Third-party contractor to FERC performing construction compliance inspections of the project, named in FERC's field inspection report of June 23, 2015 | 2015 | |
| Giles County Project[33] | 2014 | ||
| Line KNY and KM3 Replacement Project[34] | FERC's contractor for the restoration inspection of October 16, 2015 | 2014 | |
| Lucerne Residue Pipeline[35] | 2014 | ||
| Perryville Storage Laterals[36][37] | FERC's contractor for environmental compliance inspections during construction | 1 July 2010 – 1 December 2010 | 2013 |
| Petrologistics Lateral[38] | Third-party contractor to FERC performing environmental inspections of the laterals (FERC field inspection reports of July 13, 2011 and May 21, 2012) | 2012 | |
| Cane Hill Project[39] | Third-party contractor to FERC performing environmental inspections (FERC field inspection report of June 13, 2011) | 2011 | |
| Hot Spring Lateral Project[40] | FERC contractor on FERC's April 2011 environmental compliance field inspection of the project | 2011 | |
| Line 1528 Upgrade Project[41] | FERC's contractor for the environmental compliance inspection of May 20, 2011 | 2011 | |
| ML 3 Replacement Project[42] | FERC's contractor for the environmental compliance inspection of June 14 and 15, 2011 | 2011 | |
| Northeastern Tennessee Proj (NET Proj[43] | FERC's contractor on the environmental compliance inspection of the project (April 2012) | 2011 | |
| SNG Lateral[38] | Third-party contractor to FERC performing environmental inspections of the laterals (FERC field inspection reports of July 13, 2011 and May 21, 2012) | 2011 | |
| Tioga County Extension Project[44] | FERC contractor on FERC's August 2011 environmental compliance field inspection of the project | 2011 | |
| Dominion Hub III Project[45][46] | FERC's contractor for environmental compliance inspections during construction | 1 June 2010 – 1 September 2010 | 2010 |
| Eshore Parkesburg Expansion[47] | FERC's contractor on the environmental compliance inspections of the project (Nov 2010 to Nov 2011) | 2010 | |
| Fayetteville Express Pipeline[48] | Named as the FERC contractor on FERC's November 2013 restoration inspection of the project (inspection performed under contract to FERC) | 2010 | |
| Sundance Trail Expansion Project[49] | FERC's contractor for environmental compliance inspections during construction | from 1 September 2010 | 2010 |
| Wyoming Interstate Company 2010 System Enhancement Project[50] | FERC contractor on FERC's May 2011 environmental compliance field inspection of the project | 2010 | |
| ESNG 201 Seaford Expansion Project[51] | FERC's contractor for the environmental compliance inspection of August 6, 2010 | ||
| H-162 Pipeline Replacement Project[52] | FERC contractor on FERC's April 2011 environmental compliance field inspection of the project | ||
| H-164 Pipeline Project[53] | FERC's contractor for the restoration inspection of October 13, 2015 | ||
| H-305 Pipeline Project[54] | FERC's contractor for the restoration inspection of October 13, 2015 | ||
| LA Storage CP21-44[55] | |||
| LN-50 Pipeline Class Location Replacement and Testing Project[56] | FERC's contractor for the restoration inspection of November 17, 2015 | ||
| Line P Replacement Project[57] | Third-party contractor to FERC performing a construction inspection of the project (FERC field inspection report of July 27, 2011) | ||
| Low Pressure East Upgrade Project[58] | FERC's contractor for the restoration inspection of July 23, 2015 | ||
| Rockport Compressor Station Replacement Project[59] | FERC's contractor for the construction inspection of June 4, 2014 | ||
| Spindletop Expansion Project[60] | |||
| TL-400 Pipeline Replacement Project[61] | FERC's contractor for the environmental compliance inspection of June 2, 2011 | ||
| Transco/FGT Interconnection Project[62] | FERC's representative at a routine inspection of the project site on 2011-08-24, per weekly status report 3 |
References
- “FERC memorandum on organizational conflicts of interest, selection of a FERC contractor for compliance inspections, Wahpeton Expansion Project (CP22-466)”. Federal Energy Regulatory Commission. 7 May 2024. Retrieved 3 October 2026.
- “FERC construction inspection report (inspection of 2023-12-05), Venice Extension Project (CP22-15)”. Federal Energy Regulatory Commission. 3 January 2024. Retrieved 3 October 2026.
- “Weekly Environmental Status Report No. 30, Final Report (August 7 to 13, 2016), 12-Inch St. Petersburg Lateral Relocation Project (CP16-2)”. Florida Gas Transmission Company, LLC (filed with FERC). 17 August 2016. Retrieved 3 October 2026.
- “Field Inspection Report (inspection of 05/27/2026), Cedar Vale Compressor Station Project (CP25-19)”. Federal Energy Regulatory Commission. 9 July 2026. Retrieved 3 October 2026.
- “Field Inspection Report, TTC Connector Project, inspected 2026-09-01 (CP25-525)”. Federal Energy Regulatory Commission. 14 September 2026. Retrieved 4 October 2026.
- “FERC field inspection report (inspection of 2026-03-03 and 2026-03-04), CP2 LNG Project and CP Express Pipeline Project (CP22-21, CP22-22)”. Federal Energy Regulatory Commission. 24 March 2026. Retrieved 3 October 2026.
- “Construction Inspection Report (inspection of 08/22/2023), Henderson County Expansion Project (CP21-467)”. Federal Energy Regulatory Commission. 8 September 2023. Retrieved 4 October 2026.
- “Construction Inspection Report (inspection of 05/21/2024), Three Rivers Interconnection Project (CP21-113)”. Federal Energy Regulatory Commission. 13 June 2024. Retrieved 4 October 2026.
- “Construction Inspection Report, East-West Project (CP17-8)”. Federal Energy Regulatory Commission. 15 August 2018. Retrieved 4 October 2026.
- “Field Inspection Report (May 2018), Gulf Connector Expansion Project (CP16-494)”. Federal Energy Regulatory Commission staff. 7 June 2018. Retrieved 3 October 2026.
- “Construction Inspection Report (July 19, 2018 inspection), Gulf Connector Expansion Project (CP16-494)”. Federal Energy Regulatory Commission staff. 10 August 2018. Retrieved 3 October 2026.
- “Construction Inspection Report, Marshall County Mine Panel 18W Project (CP17-468)”. Federal Energy Regulatory Commission. 14 May 2018. Retrieved 4 October 2026.
- “Construction Inspection Report (January 10, 2018 inspection), Eastern System Upgrade (CP16-486)”. Federal Energy Regulatory Commission staff. 26 January 2018. Retrieved 3 October 2026.
- “Field Inspection Report (February 7, 2018 inspection), Eastern System Upgrade (CP16-486)”. Federal Energy Regulatory Commission staff. 1 March 2018. Retrieved 3 October 2026.
- “Environmental Inspection Report, Access South, Adair Southwest, and Lebanon Extension Projects, conducted May 3-4, 2017 (CP16-3)”. Federal Energy Regulatory Commission. 26 May 2017. Retrieved 4 October 2026.
- “Construction Inspection Report (March 1, 2018 inspection), Gulf Coast Expansion Project (CP16-488)”. Federal Energy Regulatory Commission staff. 15 March 2018. Retrieved 3 October 2026.
- “Construction Inspection Report (April 26, 2018 inspection), Gulf Coast Expansion Project (CP16-488)”. Federal Energy Regulatory Commission staff. 9 May 2018. Retrieved 3 October 2026.
- “Construction Inspection Report (April 3, 2018 inspection), Lone Star Project (CP16-496)”. Federal Energy Regulatory Commission staff. 13 April 2018. Retrieved 3 October 2026.
- “Construction Inspection Report (June 6, 2018 inspection), Lone Star Project (CP16-496)”. Federal Energy Regulatory Commission staff. 21 June 2018. Retrieved 3 October 2026.
- “Construction Inspection Report, Marshall County Mine Panel 17W Project (CP16-501)”. Federal Energy Regulatory Commission. 26 April 2017. Retrieved 4 October 2026.
- “Construction Inspection Report, Line YM28 and Line FM120 Modernization Project (CP17-74)”. Federal Energy Regulatory Commission. 30 November 2018. Retrieved 4 October 2026.
- “Construction Inspection Report, Paiute Pipeline Company 2018 Expansion Project (CP17-471)”. Federal Energy Regulatory Commission. 23 August 2018. Retrieved 4 October 2026.
- “Construction Inspection Report (March 14, 2018 inspection), St. Charles Parish Expansion Project (CP16-478)”. Federal Energy Regulatory Commission staff. 12 April 2018. Retrieved 3 October 2026.
- “Construction Inspection Report (August 14, 2018 inspection), St. Charles Parish Expansion Project (CP16-478)”. Federal Energy Regulatory Commission staff. 5 September 2018. Retrieved 3 October 2026.
- “Construction Inspection Report, Transco to Charleston Project (CP16-98)”. Federal Energy Regulatory Commission. 19 September 2017. Retrieved 4 October 2026.
- “Construction Inspection Report, Valley Expansion Project (CP17-257)”. Federal Energy Regulatory Commission. 25 July 2018. Retrieved 4 October 2026.
- “Construction Inspection Report, Wekiva Parkway Relocation Project (CP17-79)”. Federal Energy Regulatory Commission. 23 July 2018. Retrieved 4 October 2026.
- “Environmental Inspection Report, Delaware River Pipeline Replacement Project, inspected 3/28/2017 (CP16-27)”. Federal Energy Regulatory Commission. 13 April 2017. Retrieved 4 October 2026.
- “Request for Authorization to Place Facilities In-Service, Western Kentucky Lateral Project (CP15-105)”. Texas Gas Transmission, LLC (filed with FERC). 5 August 2016. Retrieved 4 October 2026.
- “FERC Field Inspection Report, Bradley Lateral Project (inspection of September 28, 2016), Enable Gas Transmission, L.L.C. (CP14-503)”. FERC. 29 December 2016. Retrieved 4 October 2026.
- “FERC Field Inspection Report, H-312 Pipeline Project (inspection of June 6, 2016), Equitrans, L.P. (CP14-523)”. FERC. 1 July 2016. Retrieved 4 October 2026.
- “FERC field inspection report (June 23, 2015), Lawrence County Expansion Project (CP15-19)”. FERC (inspection by Tetra Tech, Inc. under contract to FERC). 7 July 2015. Retrieved 4 October 2026.
- “FERC Field Inspection Report, Giles County Project, April 1, 2014 (CP13-125)”. Federal Energy Regulatory Commission. 1 April 2014. Retrieved 4 October 2026.
- “FERC Field Inspection Report, Lines KM3 and KNY Replacement Project (inspection of October 16, 2015), National Fuel Gas Supply Corporation (CP14-107)”. FERC. 17 December 2015. Retrieved 4 October 2026.
- “FERC Construction Inspection Report, Lucerne Residue Pipeline Project, May 13, 2014 (CP13-509)”. Federal Energy Regulatory Commission. 13 May 2014. Retrieved 4 October 2026.
- “Environmental Compliance Inspection Report, July 15, 2010, Crowville Salt Dome Storage Project (CP09-418)”. Federal Energy Regulatory Commission. 2 August 2010. Retrieved 4 October 2026.
- “Environmental Compliance Inspection Report, December 2, 2010, Crowville Salt Dome Storage Project (CP09-418)”. Federal Energy Regulatory Commission. 22 December 2010. Retrieved 4 October 2026.
- “FERC field inspection report (July 13, 2011), Acadian Gas Petrologistics and SNG Lateral Projects (CP11-162, CP11-163)”. FERC (inspection by Tetra Tech, Inc. under contract to FERC). 26 August 2011. Retrieved 4 October 2026.
- “FERC field inspection report (June 13, 2011), Cane Hill Compressor Station Project (CP11-21)”. FERC (inspection by Tetra Tech, Inc. under contract to FERC). 13 June 2011. Retrieved 4 October 2026.
- “Environmental Compliance Inspection Report, Hot Spring Lateral Project, April 6, 2011 (CP10-471)”. Federal Energy Regulatory Commission. 22 April 2011. Retrieved 4 October 2026.
- “Environmental Compliance Inspection Report, Line 1528 Upgrade Project (inspection of May 20, 2011), Columbia Gas Transmission, LLC (CP10-439)”. FERC. 9 June 2011. Retrieved 4 October 2026.
- “FERC Field Inspection Report, Questar Main Line 3 Replacement Project (inspection of June 14 and 15, 2011) (CP11-62)”. FERC. 1 July 2011. Retrieved 4 October 2026.
- “Environmental Compliance Inspection Report, Northeastern Tennessee (NET) Project, inspection of 2012-04-26 (CP10-89)”. Federal Energy Regulatory Commission. 5 June 2012. Retrieved 4 October 2026.
- “Environmental Compliance Inspection Report, Tioga County Extension Project, August 4, 2011 (CP10-493)”. Federal Energy Regulatory Commission. 26 August 2011. Retrieved 4 October 2026.
- “Environmental Compliance Inspection Report, June 1, 2010, Dominion Hub III Project (CP09-18)”. Federal Energy Regulatory Commission. 17 June 2010. Retrieved 4 October 2026.
- “Environmental Compliance Inspection Report, September 10, 2010, Dominion Hub III Project (CP09-18)”. Federal Energy Regulatory Commission. 20 October 2010. Retrieved 4 October 2026.
- “Environmental Compliance Inspection Report, Mainline Extension Interconnect Project, inspection of 2010-11-08 (CP10-76)”. Federal Energy Regulatory Commission. 23 November 2010. Retrieved 4 October 2026.
- “Field Inspection Report (Nov 19-20, 2013), Fayetteville Express Pipeline Project (CP09-433)”. FERC staff report (prepared by a FERC contractor). 16 December 2013. Retrieved 4 October 2026.
- “Environmental Compliance Inspection Report, Sundance Trail Expansion Project (CP09-415)”. Federal Energy Regulatory Commission. 24 September 2010. Retrieved 4 October 2026.
- “Environmental Compliance Inspection Report, WIC 2010 System Enhancement Project, May 18, 2011 (CP10-13)”. Federal Energy Regulatory Commission. 9 June 2011. Retrieved 4 October 2026.
- “FERC Field Inspection Report, ESNG 201 Seaford Expansion Project (inspection of August 6, 2010), Eastern Shore Natural Gas Company (CP10-51)”. FERC. 20 August 2010. Retrieved 4 October 2026.
- “Environmental Compliance Monitoring Report, H-162 Pipeline Replacement Project, April 13-14, 2011 (CP09-44)”. Federal Energy Regulatory Commission. 12 May 2011. Retrieved 4 October 2026.
- “FERC Field Inspection Report, H-164 Pipeline Project (inspection of October 13, 2015), Equitrans, L.P. (CP14-90)”. FERC. 20 November 2015. Retrieved 4 October 2026.
- “FERC Field Inspection Report, H-305 Pipeline Project (inspection of October 13, 2015), Equitrans, L.P. (CP14-130)”. FERC. 20 November 2015. Retrieved 4 October 2026.
- “Field Inspection Report (inspection of 06/24/2025), Hackberry Storage Project (CP21-44 and CP24-487)”. Federal Energy Regulatory Commission. 14 July 2025. Retrieved 4 October 2026.
- “FERC Field Inspection Report, LN-50 Pipeline Class Location Replacement and Testing Project (inspection of November 17, 2015), Dominion Transmission, Inc. (CP14-499)”. FERC. 21 December 2015. Retrieved 4 October 2026.
- “FERC field inspection report (July 27, 2011), Line P Replacement Project (CP11-66)”. FERC (inspection by Tetra Tech, Inc. under contract to FERC). 26 August 2011. Retrieved 4 October 2026.
- “FERC Field Inspection Report, Low Pressure East Upgrade Project (inspection of July 23, 2015), Equitrans, L.P. (CP13-79)”. FERC. 27 August 2015. Retrieved 4 October 2026.
- “FERC Field Inspection Report, Rockport Compressor Station Replacement Project (inspection of June 4, 2014), Columbia Gas Transmission, LLC (CP13-81)”. FERC. 17 June 2014. Retrieved 4 October 2026.
- “Field Inspection Report (inspection of 07/07/2026), Spindletop Expansion Project (CP25-167)”. Federal Energy Regulatory Commission. 16 July 2026. Retrieved 3 October 2026.
- “FERC Field Inspection Report, TL-400 Replacement Project (inspection of June 2, 2011), Dominion Transmission, Inc. (CP11-71)”. FERC. 20 June 2011. Retrieved 4 October 2026.
- “Weekly Status Report No. 3, Transco Interconnect, Gulf LNG Pipeline, LLC (CP11-486)”. Gulf LNG Pipeline, LLC (filed with FERC). 1 September 2011. Retrieved 4 October 2026.