Three Rivers Interconnection Project
From the ProvenHand pipeline wiki
Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.
Three Rivers Interconnection Project is a natural gas pipeline lateral in Illinois, operated by Alliance Pipeline L.P.. Construction began in 2024.
| Three Rivers Interconnection Project | |
|---|---|
| Also called | Related Authorizations for Three Rivers Interconnection Project[1] |
| General information | |
| Kind | Pipeline project[2] |
| Project type | Lateral[3] |
| Status | In service[3][4] |
| Commodity | Natural gas[3] |
| Owner and operator | |
| State | Illinois[2][3] |
| Counties | Grundy[5] |
| Approved | 17 March 2023[2][5] |
| Construction started | 28 March 2024[6] |
| In service | 16 September 2024[3] or 30 September 2024[4][sources disagree] |
| FERC docket | CP21-113[2] |
| Contractors | |
| Technical information | |
| Length | 2.8 mi[2][3] or 2.9 mi[5][sources disagree] |
| Pipe size | 20"[3][5] |
| Capacity | 210 MMcf/d (FERC project list)[2][3] |
| Cost | $27.7 million (EIA estimate; no dollar year given)[3][5] |
| On ProvenHand | |
| Hands listed | 0 |
Three Rivers Interconnection Project is a natural gas pipeline lateral in Illinois, operated by Alliance Pipeline L.P.. Construction began in 2024.
Contractorsedit
| Contractor | Work | Scope |
|---|---|---|
| North Country Directional Drilling, LLC[7] | HDD and bore | Four 20-inch steel HDD crossings in Grundy County IL, including a hard-rock bore under the Illinois River |
Inspection
Crossings
| Feature | Method | Contractor |
|---|---|---|
| Illinois River[7][9] | HDD | North Country Directional Drilling, LLC |
| Illinois and Michigan Canal[9] | HDD | |
| Lock Road[9] | HDD | |
| Railroad[9] | HDD |
Sources disagree
These sources give different values for the same fact. Each value is listed with the sources that give it.
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Three Rivers Interconnection Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “FERC eLibrary docket CP21-113”. Federal Energy Regulatory Commission. 1 April 2021. Retrieved 3 October 2026.
- “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
- “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
- “Notice of Commencement of Service, Three Rivers Interconnection Project (CP21-113)”. Alliance Pipeline L.P. (filed with FERC). 3 October 2024. Retrieved 4 October 2026.
- “Order Issuing Certificate, Alliance Pipeline L.P., Three Rivers Interconnection Project (CP21-113)”. Federal Energy Regulatory Commission. 17 March 2023. Retrieved 4 October 2026.
- “Bi-Weekly Status Report No. 1, Three Rivers Interconnection Project (CP21-113)”. Alliance Pipeline L.P. (filed with FERC). 25 April 2024. Retrieved 4 October 2026.
- “HDD Project Videos & Press Coverage | NCDD”. North Country Directional Drilling, LLC. Retrieved 3 October 2026.
- “Construction Inspection Report (inspection of 05/21/2024), Three Rivers Interconnection Project (CP21-113)”. Federal Energy Regulatory Commission. 13 June 2024. Retrieved 4 October 2026.
- “Request for Notice to Proceed with Construction, Three Rivers Interconnection Project (CP21-113)”. Alliance Pipeline L.P. (filed with FERC). 5 March 2024. Retrieved 4 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.