Venice Extension Project

From the ProvenHand pipeline wiki

Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.

Venice Extension Project is a natural gas pipeline expansion in Louisiana, operated by Texas Eastern Transmission, LP. Construction began in 2023. It runs 3 miles of 42" pipe.

Venice Extension Project
Also calledVenice Lateral Project[1]
General information
KindPipeline project[2]
Project typeExpansion[3]
StatusIn service[3]
CommodityNatural gas[3]
Owner and operator
Facility projects
StateLouisiana[3][4]
CountiesIberville, Lafourche, Plaquemines, Pointe Coupee[1]
Approved26 September 2023[4] or 22 September 2023[1][sources disagree]
Construction started13 November 2023[5]
In service15 December 2024[3] or 10 January 2025[6][sources disagree]
FERC docketCP22-15[2]
Technical information
Length3 mi[1][3][4]
Pipe size42 in[3] or 36 in[1][sources disagree]
Capacity1260 MMcf/d (FERC project list)[3][4]
Cost$360.3 million (EIA estimate; no dollar year given)[3] or $422,678,561 (post-construction cost report, July 2025; Exhibit K estimate $360,306,366)[7][sources disagree]
On ProvenHand
Hands listed0

Venice Extension Project is a natural gas pipeline expansion in Louisiana, operated by Texas Eastern Transmission, LP. Construction began in 2023. It runs 3 miles of 42" pipe.

Inspection

FirmScope
Tetra Tech, Inc.[8]Environmental compliance inspections for FERC staff

Spreads

Spread
Line 40 Pipeline Replacement[1]

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Approved
  • 26 September 2023[4]
  • 22 September 2023[1]
Cost
  • $360.3 million (EIA estimate; no dollar year given)[3]
  • $422,678,561 (post-construction cost report, July 2025; Exhibit K estimate $360,306,366)[7]
Diameters
In service
  • 15 December 2024[3]
  • 10 January 2025[6]

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Venice Extension Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “Order Issuing Certificate and Granting Abandonment, Texas Eastern Transmission, LP, Venice Extension Project (CP22-15)”. Federal Energy Regulatory Commission. 22 September 2023. Retrieved 3 October 2026.
  2. “FERC eLibrary docket CP22-15”. Federal Energy Regulatory Commission. 10 November 2021. Retrieved 3 October 2026.
  3. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  4. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  5. “Notice of Commencement of Construction, Venice Extension Project (CP22-15)”. Texas Eastern Transmission, LP (filed with FERC). 14 November 2023. Retrieved 3 October 2026.
  6. “Notice of Commencement of Service (Larose and New Roads Compressor Stations), Venice Extension Project (CP22-15)”. Texas Eastern Transmission, LP (filed with FERC). 13 January 2025. Retrieved 3 October 2026.
  7. “Post Construction Cost Report, Venice Extension Project (CP22-15)”. Texas Eastern Transmission, LP (filed with FERC). 10 July 2025. Retrieved 3 October 2026.
  8. “FERC construction inspection report (inspection of 2023-12-05), Venice Extension Project (CP22-15)”. Federal Energy Regulatory Commission. 3 January 2024. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.