MASS Project is a natural gas pipeline expansion, operated by Enable Gas Transmission, LLC. Construction began in 2020 and the line entered service in 2021. It runs 1.5 miles of 24" pipe.

MASS Project
General information
KindPipeline project[1]
Project typeExpansion[1]
StatusIn service[1][2]
CommodityNatural gas[1]
Operator
Owner and operator
StateOK[1] or AR, LA, OK[4][sources disagree]
CountiesArkansas: Clark, Jackson
Louisiana: Richland

Oklahoma: Grady, McClain
[4]
Construction started3 September 2020[5]
In serviceApril 2021[1]
FERC docketCP20-482[1]
Technical information
Length1.5 mi[1]
Pipe size24"[2]
Capacity100 MMcf/d additional capacity (EIA)[1]
Cost$35.9 million (EIA estimate; no dollar year given)[1]
On ProvenHand
Hands listed0

MASS Project is a natural gas pipeline expansion, operated by Enable Gas Transmission, LLC. Construction began in 2020 and the line entered service in 2021. It runs 1.5 miles of 24" pipe.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
States

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on MASS Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  2. “Final Status Report, Merge, Arkoma SCOOP & STACK (MASS) Project (CP20-482)”. Enable Gas Transmission, LLC (filed with FERC). 28 July 2021. Retrieved 4 October 2026.
  3. “FERC eLibrary docket CP20-482”. Federal Energy Regulatory Commission. 17 June 2020. Retrieved 3 October 2026.
  4. “Prior Notice of Blanket Certificate Activity, MASS Project (CP20-482)”. Enable Gas Transmission, LLC (filed with FERC). 17 June 2020. Retrieved 4 October 2026.
  5. “Weekly Status Report (first), MASS Project (CP20-482)”. Enable Gas Transmission, LLC (filed with FERC). 11 September 2020. Retrieved 4 October 2026.