Medicine Bow Expansion Project is a natural gas pipeline expansion, operated by Wyoming Interstate Company, L.L.C..

Medicine Bow Expansion Project
Also calledWIG Medicine Bow 08 Expansion[1]
General information
KindPipeline project[1]
Project typeExpansion[2][3]
StatusIn service[2]
CommodityNatural gas[2]
Owner and operator
Operator
Facility project
StateWY[1] or CO, WY[2][sources disagree]
CountiesConverse[4]
Approved18 October 2007[1]
In service29 October 2008[2] or 30 October 2008[4][sources disagree]
FERC docketCP07-395[1]
Technical information
Capacity330 MMcf/d (FERC project list)[1][2]
Cost$32 million (EIA estimate; no dollar year given)[2] or $41,461,846 total actual project cost (estimate $32,073,500)[5][sources disagree]
On ProvenHand
Hands listed0

Medicine Bow Expansion Project is a natural gas pipeline expansion, operated by Wyoming Interstate Company, L.L.C..

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Cost
  • $32 million (EIA estimate; no dollar year given)[2]
  • $41,461,846 total actual project cost (estimate $32,073,500)[5]
In service
  • 29 October 2008[2]
  • 30 October 2008[4]
States

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Medicine Bow Expansion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “FERC eLibrary docket CP07-395”. Federal Energy Regulatory Commission. 6 June 2007. Retrieved 3 October 2026.
  4. “Notice of Commencement of Service, Medicine Bow Expansion Project (CP07-395)”. Wyoming Interstate Company, Ltd. (filed with FERC). 7 November 2008. Retrieved 4 October 2026.
  5. “Actual cost of facilities constructed, Medicine Bow Expansion Project (CP07-395)”. Wyoming Interstate Company, Ltd. (filed with FERC). 30 April 2009. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.