NNG West Leg II Expansion
From the ProvenHand pipeline wiki
NNG West Leg II Expansion is a natural gas pipeline expansion in Nebraska, operated by Northern Natural Gas Company. It was built and entered service in 2008. It runs 12 miles of 8", 30" pipe.
| NNG West Leg II Expansion | |
|---|---|
| Also called | Northern Natural Gas West Leg II Project[1] |
| General information | |
| Kind | Pipeline project[2] |
| Project type | Expansion[2] |
| Status | In service[2] |
| Commodity | Natural gas[2] |
| Operator | |
| Owner and operator | |
| State | Nebraska[2] |
| Counties | Iowa: Woodbury Nebraska: Colfax, Platte[3] |
| Construction started | 8 July 2008[3] |
| In service | November 2008[2] |
| FERC docket | CP08-97[2] |
| Contractors | |
| Technical information | |
| Length | 12 mi[2] |
| Pipe size | 8", 30"[2] |
| Capacity | 11 MMcf/d additional capacity (EIA)[2] |
| Cost | $9.12 million (EIA estimate; no dollar year given)[2] |
| On ProvenHand | |
| Hands listed | 0 |
NNG West Leg II Expansion is a natural gas pipeline expansion in Nebraska, operated by Northern Natural Gas Company. It was built and entered service in 2008. It runs 12 miles of 8", 30" pipe.
Contractorsedit
| Contractor | Work | Spread | Years |
|---|---|---|---|
| H D Griffin[3] | Prime | WL2 Columbus BL Loop | from 8 July 2008 |
| Michels Pipeline, Inc.[3] | Prime | WL2 SSC-Paullina C-Line Extension | from 12 August 2008 |
Spreads
| Spread | Prime contractor | Dates |
|---|---|---|
| WL2 Columbus BL Loop[3] | H D Griffin | from 8 July 2008 |
| WL2 SSC-Paullina C-Line Extension[3] | Michels Pipeline, Inc. | from 12 August 2008 |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on NNG West Leg II Expansion? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “FERC eLibrary docket CP08-97”. Federal Energy Regulatory Commission. 25 March 2008. Retrieved 3 October 2026.
- “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
- “West Leg II prior-notice project weekly report, November 8-14, 2008 (CP08-97)”. Northern Natural Gas Company (filed with FERC). 20 November 2008. Retrieved 4 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.