Southern Natural Gas South System Expansion Project is a pipeline project in Alabama, Georgia, Louisiana and Mississippi, operated by Southern Natural Gas Company South System. It runs 114.2 miles.
| Southern Natural Gas South System Expansion Project | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Operator | Southern Natural Gas Company South System[1] |
| Owner and operator | |
| States | Alabama, Georgia, Louisiana, Mississippi[1] |
| Approved | 18 September 2002[1] |
| FERC docket | CP02-1[1] |
| Contractors | |
| Technical information | |
| Length | 114.2 mi[1] |
| Capacity | 330 MMcf/d (FERC project list)[1] |
| On ProvenHand | |
| Hands listed | 0 |
Southern Natural Gas South System Expansion Project is a pipeline project in Alabama, Georgia, Louisiana and Mississippi, operated by Southern Natural Gas Company South System. It runs 114.2 miles.
Contractorsedit
| Contractor | Work | Scope | Years |
|---|---|---|---|
| Latex Construction[2] | Prime | South System Expansion Phase II: 20.7 miles of 36-inch loop and 3.4 miles of 30-inch loop in Lauderdale County, MS and Marengo, Hale and Perry Counties, AL; completed 2003 (client listed as El Paso/Southern Natural Gas) | until 1 January 2003 |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Southern Natural Gas South System Expansion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
- “Latex Construction Company - Completed Projects (2005-2006 site)”. Latex Construction Company. Archived from the original on 27 November 2005. Retrieved 6 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.