Texas Eastern Transmission Line 31 Expansion Project
From the ProvenHand pipeline wiki
Texas Eastern Transmission Line 31 Expansion Project is a natural gas pipeline expansion in Mississippi, operated by Texas Eastern Transmission, LP. It runs 11.8 miles of 36" pipe.
| Texas Eastern Transmission Line 31 Expansion Project | |
|---|---|
| Also called | Line 31 Expansion Project[1] |
| General information | |
| Kind | Pipeline project[2] |
| Project type | Expansion[1][2] |
| Status | Proposed[1][3] |
| Commodity | Natural gas[1][3] |
| Owner and operator | |
| Operator | |
| Facility project | |
| State | Mississippi[1][4] |
| Counties | Hinds, Madison[4] |
| FERC docket | CP26-75[2] |
| Contractors | |
| Technical information | |
| Length | 11.8 mi[1][3] |
| Pipe size | 36 in[1] or 16 in, 36 in[4][sources disagree] |
| Capacity | 125 MMcf/d additional capacity (EIA)[1] or 125,000 Dth/d of additional transportation service to Entergy Mississippi's proposed Traceview Advanced Power Station[3][sources disagree] |
| Cost | $131 million (EIA estimate; no dollar year given)[1][4] |
| On ProvenHand | |
| Hands listed | 0 |
Texas Eastern Transmission Line 31 Expansion Project is a natural gas pipeline expansion in Mississippi, operated by Texas Eastern Transmission, LP. It runs 11.8 miles of 36" pipe.
Contractorsedit
| Contractor | Work | Scope |
|---|---|---|
| Hoover & Keith Inc.[3] | Acoustical consultant (noise analysis) | Noise analysis of the Ridgeland Compressor Station at full load (July 2025), cited in the EA |
Sources disagree
These sources give different values for the same fact. Each value is listed with the sources that give it.
| Fact | Values given |
|---|---|
| Capacity | |
| Diameters |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Texas Eastern Transmission Line 31 Expansion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
- “FERC eLibrary docket CP26-75”. Federal Energy Regulatory Commission. 23 January 2026. Retrieved 3 October 2026.
- “Environmental Assessment for the Line 31 Expansion Project (CP26-75)”. Federal Energy Regulatory Commission. 24 July 2026. Retrieved 3 October 2026.
- “Abbreviated Application for Certificate of Public Convenience and Necessity, Line 31 Expansion Project (CP26-75)”. Texas Eastern Transmission, LP (filed with FERC). 23 January 2026. Retrieved 3 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.