Texas to Louisiana Energy Pathway
From the ProvenHand pipeline wiki
Texas to Louisiana Energy Pathway is a natural gas pipeline expansion in Louisiana and Texas, operated by Transcontinental Gas Pipe Line Company, LLC. Construction began in 2024.
| Texas to Louisiana Energy Pathway | |
|---|---|
| Also called | Texas to Louisiana Project[1] |
| General information | |
| Kind | Pipeline project[2] |
| Project type | Expansion[2] |
| Status | In service[2] |
| Commodity | Natural gas[2] |
| Operator | |
| Owner and operator | |
| Facility projects | |
| States | Louisiana, Texas[2] |
| Counties | Fort Bend, Hardin, Victoria[1] |
| Approved | 18 January 2024[1] |
| Construction started | 15 July 2024[4] |
| In service | 25 February 2025[2] or 1 April 2025[5][sources disagree] |
| FERC docket | CP22-495[2] |
| Contractors | |
| Technical information | |
| Capacity | 364 MMcf/d additional capacity (EIA)[2] |
| Cost | $92 million (EIA estimate; no dollar year given)[2] or approximately $91,781,074[1][sources disagree] |
| On ProvenHand | |
| Hands listed | 0 |
Texas to Louisiana Energy Pathway is a natural gas pipeline expansion in Louisiana and Texas, operated by Transcontinental Gas Pipe Line Company, LLC. Construction began in 2024.
Contractorsedit
| Contractor | Work | Scope |
|---|---|---|
| Ranger Plant Constructional Co.[6] | Construction contractor named on the key personnel list (scope not stated) | |
| Hoover & Keith Inc.[7] | Acoustical consulting (sound surveys and noise report) | Pre-construction sound survey at Compressor Station 40; noise report for Compressor Station 33 |
Sources disagree
These sources give different values for the same fact. Each value is listed with the sources that give it.
| Fact | Values given |
|---|---|
| Cost | |
| In service |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Texas to Louisiana Energy Pathway? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “Order Issuing Certificate, Texas to Louisiana Energy Pathway Project (CP22-495)”. FERC. 18 January 2024. Retrieved 3 October 2026.
- “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
- “FERC eLibrary docket CP22-495”. Federal Energy Regulatory Commission. 9 August 2022. Retrieved 3 October 2026.
- “Monthly Construction Status Report (July 2024), Texas to Louisiana Energy Pathway Project (CP22-495)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 14 August 2024. Retrieved 3 October 2026.
- “Notice of commencement of full service on 04/01/2025, Texas to Louisiana Energy Pathway Project (CP22-495)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 2 April 2025. Retrieved 3 October 2026.
- “Request for notice to proceed with construction and variance TLEP-VAR-001, Texas to Louisiana Energy Pathway Project (CP22-495)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 17 June 2024. Retrieved 3 October 2026.
- “Implementation Plan, Texas to Louisiana Energy Pathway Project (CP22-495)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 20 February 2024. Retrieved 3 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.