Tioga Pathway Project

From the ProvenHand pipeline wiki

Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.

Tioga Pathway Project is a natural gas pipeline expansion in Pennsylvania, operated by National Fuel Gas Supply Corporation.

Tioga Pathway Project
Also calledTioga Pathway Expansion[1]
General information
KindPipeline project[1]
Project typeExpansion[2]
StatusUnder construction[2]
CommodityNatural gas[2]
Owner and operator
StatePennsylvania[2][3][4]
CountiesPotter, Tioga[4]
Approved5 May 2025[3]
FERC docketCP24-514[1]
Contractors
Technical information
Length23.3 mi[3] or 20 mi[2][sources disagree]
Pipe size12", 20"[4]
Capacity190 MMcf/d (FERC project list)[2][3]
Capacity added190,000 dekatherms per day of new transportation capacity[4]
Cost$100 million (EIA estimate; no dollar year given)[2] or $101,168,022 (National Fuel estimate, 2024 application)[4][sources disagree]
On ProvenHand
Hands listed0

Tioga Pathway Project is a natural gas pipeline expansion in Pennsylvania, operated by National Fuel Gas Supply Corporation.

Contractorsedit

ContractorWorkScopeYears
Right-Of-Way Clearing & Maintenance, Inc.[5]Clearing and reclamationClearing; listed as Tioga Pathway in Potter and Tioga Counties PA (Michels Pipeline/National Fuel Gas)until 1 January 2026

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Cost
  • $100 million (EIA estimate; no dollar year given)[2]
  • $101,168,022 (National Fuel estimate, 2024 application)[4]
Length

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Tioga Pathway Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC eLibrary docket CP24-514”. Federal Energy Regulatory Commission. 21 August 2024. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  4. “Notice of Application and Establishing Intervention Deadline, National Fuel Gas Supply Corporation, Tioga Pathway Project (CP24-514)”. FERC (public notice, eLibrary). 30 August 2024. Retrieved 4 October 2026.
  5. “Projects”. Right-Of-Way Clearing & Maintenance, Inc. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.