TransCameron Pipeline

From the ProvenHand pipeline wiki

Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.

TransCameron Pipeline is a natural gas pipeline lateral in Louisiana, operated by Venture Global. It entered service in 2021.[1]

TransCameron Pipeline
Also calledTransCameron
General information
Project typeLateral[1]
StatusIn service[1]
CommodityNatural gas[1]
OperatorVenture Global
Operator
Owner and operator
StateLouisiana[1]
CountiesCameron[4]
Approved21 February 2019[4][5]
In service7 April 2021[1][6]
FERC docketCP15-551[5]
Contractors
Technical information
Length24 mi[1] or 23.4 mi[4][sources disagree]
Pipe size42"[1][4]
Capacity1900 MMcf/d additional capacity (EIA)[1] or up to 2,125,000 Dth/d (FERC order)[4][sources disagree]
Cost$344.545 million (EIA estimate; no dollar year given)[1]
On ProvenHand
Hands listed0

TransCameron Pipeline is a natural gas pipeline lateral in Louisiana, operated by Venture Global. It entered service in 2021.[1]

Contractorsedit

ContractorWorkScope
WHC[2]31 km of 42-inch
WHC[2]Mechanized weldingMechanized welding (RMS MOWII system) of 31 km of 42-inch pipe on the Venture Global TransCameron pipeline

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Capacity
  • 1900 MMcf/d additional capacity (EIA)[1]
  • up to 2,125,000 Dth/d (FERC order)[4]
Length

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on TransCameron Pipeline? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  2. “Projects (MOWII)”. RMS Welding Systems. Retrieved 3 October 2026.
  3. “FERC eLibrary docket CP15-551”. Federal Energy Regulatory Commission. 4 September 2015. Retrieved 3 October 2026.
  4. “Order Granting Authorizations under Sections 3 and 7 of the Natural Gas Act, Venture Global Calcasieu Pass, LLC and TransCameron Pipeline, LLC (CP15-550, CP15-551)”. FERC. 21 February 2019. Retrieved 3 October 2026.
  5. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  6. “Letter order granting TransCameron Pipeline's request to commence service (CP15-551)”. FERC. 7 April 2021. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.