Virginia Southside Expansion Project II is a natural gas pipeline in North Carolina, South Carolina and Virginia, operated by Transcontinental Gas Pipe Line Company, LLC.

Virginia Southside Expansion Project II
General information
KindPipeline project[1]
Project typeLateral[2] or Expansion[3][sources disagree]
StatusIn service[2]
CommodityNatural gas[2]
Owner and operator
StatesNorth Carolina, South Carolina, Virginia[1][2]
CountiesBrunswick, Greensville[4]
Approved7 July 2016[1]
In service4 December 2017[2] or 1 December 2017[5][sources disagree]
FERC docketCP15-118[1]
Contractors
Technical information
Length4.3 mi[1] or 4.9 mi[2][sources disagree]
Pipe size24"[2]
Capacity250 MMcf/d (FERC project list)[1][2]
Cost$190.8 million (EIA estimate; no dollar year given)[2]
On ProvenHand
Hands listed0

Virginia Southside Expansion Project II is a natural gas pipeline in North Carolina, South Carolina and Virginia, operated by Transcontinental Gas Pipe Line Company, LLC.

Contractorsedit

ContractorWorkScope
Troy Construction[4]PrimeListed 2017 as contractor: 4 miles of new 24-inch and a meter station, Brunswick to Greensville County, VA

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Project type
In service
  • 4 December 2017[2]
  • 1 December 2017[5]
Length

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Virginia Southside Expansion Project II? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  2. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  3. “FERC eLibrary docket CP15-118”. Federal Energy Regulatory Commission. 23 March 2015. Retrieved 3 October 2026.
  4. “Ongoing Projects: Construction Underway (Pipeline News, September 2017)”. Pipeline News. September 2017. Retrieved 3 October 2026.
  5. “Notification of Commencement of Service, Virginia Southside Expansion Project II (CP15-118)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 4 December 2017. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.