8-Inch NGL Pipeline - McKenzie and Dunn Counties

From the ProvenHand pipeline wiki

8-Inch NGL Pipeline - McKenzie and Dunn Counties is an NGL pipeline in North Dakota, operated by ONEOK Bakken Pipeline, L.L.C.. Construction began in 2016. It runs 38 miles of 8" pipe.

8-Inch NGL Pipeline - McKenzie and Dunn Counties
Also calledBear Creek NGL Pipeline[1]
General information
KindPipeline project[2]
CommodityNGL[3]
Owner and operator
StateNorth Dakota[2]
CountiesDunn, McKenzie[4]
Approved23 March 2016[3]
Construction started21 April 2016[5]
North Dakota PSC casePU-15-801[2]
Contractors
Technical information
Length38 mi[3]
Pipe size8"[3]
Cost$45,000,000 estimated investment (PSC siting spreadsheet)[3]
On ProvenHand
Hands listed0

8-Inch NGL Pipeline - McKenzie and Dunn Counties is an NGL pipeline in North Dakota, operated by ONEOK Bakken Pipeline, L.L.C.. Construction began in 2016. It runs 38 miles of 8" pipe.

Contractorsedit

ContractorWorkSpread
Jomax Construction Co., Inc.[1]construction contractor listed among the pre-construction meeting attendees (role in the build not stated)
Sterling Construction Co.[1]construction contractor listed among the pre-construction meeting attendees (role in the build not stated)
Site Energy Construction[1]construction contractor listed among the pre-construction meeting attendees (role in the build not stated)
Jomax Construction Co., Inc.[5]PrimeSpread 1
Sterling Construction Co.[5]PrimeSpread 2
Site Energy Construction[5]PrimeSpread 3

Inspection

Spreads

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on 8-Inch NGL Pipeline - McKenzie and Dunn Counties? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “Preconstruction meeting minutes, template letter to landowners, case PU-15-801, docket 38”. Filed with the North Dakota Public Service Commission. 13 April 2016. Retrieved 3 October 2026.
  2. “North Dakota Public Service Commission: case search (pipeline siting)”. North Dakota Public Service Commission. Retrieved 3 October 2026.
  3. “North Dakota PSC siting applications spreadsheet (siting cases 2005 to present)”. North Dakota Public Service Commission. Retrieved 3 October 2026.
  4. “ND PSC case PU-15-801 docket list: 8-Inch NGL Pipeline - McKenzie and Dunn Counties”. North Dakota Public Service Commission. Retrieved 3 October 2026.
  5. “Topsoil Inspection Report, case PU-15-801, docket 47”. Wenck Associates, Inc. (filed with the North Dakota Public Service Commission). 28 June 2016. Retrieved 3 October 2026.
  6. “Construction Inspection Report, case PU-15-801, docket 53”. Wenck Associates, Inc. (filed with the North Dakota Public Service Commission). 31 August 2016. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.