Alberta Clipper (Line 67), US portion is a crude oil pipeline in North Dakota, Minnesota and Wisconsin, operated by Enbridge. Construction began in 2009 and the line entered service in 2010.[1]

Alberta Clipper (Line 67), US portion
Also calledAlberta Clipper, Line 67
General information
CommodityCrude oil
OperatorEnbridge
StatesNorth Dakota, Minnesota, Wisconsin
Construction started2009
In service2010
Contractors
Technical information
Pipe size36"
WeldingMechanized[4]
On ProvenHand
Hands listed0

Alberta Clipper (Line 67), US portion is a crude oil pipeline in North Dakota, Minnesota and Wisconsin, operated by Enbridge. Construction began in 2009 and the line entered service in 2010.[1]

Contractorsedit

ContractorWorkScopeSpreadYears
Precision Pipeline[3]206 miles in Minnesota (2009)
Michels[1]Two spreads: 112 km in ND/MN and 107 km Snake River to Clearbrook, MN
U.S. Pipeline[1]Member of the Global Pipeline Partners JV (with Michels and Precision)
Hoover Construction Company[5][6]Rock drilling and blastingPipeline rock drilling and blasting, Minnesota and Wisconsin1 January 2009
U.S. Pipeline, Inc.[7]Prime87 miles of dual 20-inch and 36-inch in Minnesota1 January 2009
U.S. Pipeline, Inc.[8]PrimeMember of Global Pipeline Partners, the three-contractor partnership (with Michels Corp. and Precision Pipeline LLC) that began building the 326-mile, 36-inch U.S. segment in August 2009; completion expected mid-2010from 1 August 2009
U.S. Pipeline, Inc.[9]PrimeMember of Global Pipeline Partners, the three-contractor partnership (with Michels Corp. and Precision Pipeline) doing the U.S. construction; projected completion early 2010from 1 August 2009
Michels Pipeline Construction, Inc.[4]PrimeSpread 1: 69.7 miles of 36-inch in northern North Dakota and Minnesota, Serimax automatic welding; 95 road crossings and 25 open-cut water crossingsSpread 120 August 2009 – 1 April 2010
Michels Pipeline Construction, Inc.[4]PrimeSpread 2: 67 miles of 36-inch from the Snake River to Clearbrook, MNSpread 2from 21 August 2009
Michels Pipeline, Inc.[10]Pipeline construction (role not stated)Listed on the firm's 2014 pipeline page (as Michels Pipeline Construction) among five of the largest pipeline projects it had recently worked on; role and years not stated
Precision Pipeline, LLC[3]Prime206 miles of 36-inch and 20-inch, Minnesotauntil 1 January 2009
Michels Directional Crossings[11]HDD and boreHDD crossings for the 36-inch Alberta Clipper from Neche, ND toward Superior: 47,600 ft of 36-inch pipe in crossings of 1,300 to 5,200 ft (33 crossings together with Southern Lights)

Spreads

SpreadPrime contractorDates
Spread 1[4]Michels Pipeline Construction, Inc.20 August 2009 – 1 April 2010
Spread 2[4]Michels Pipeline Construction, Inc.from 21 August 2009

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Alberta Clipper (Line 67), US portion? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. offshore-technology.com
  2. sec.gov · d10k.htm
  3. “All Projects - Precision Pipeline, LLC | Infrastructure and Utility Pipeline Contractor”. Precision Pipeline, LLC. Retrieved 3 October 2026.
  4. “Challenges Of Overlapping Construction On 3 Major Pipeline Projects”. Underground Construction. May 2010. Retrieved 6 October 2026.
  5. “2009 Alberta Clipper (Minnesota) – Hoover Construction”. Hoover Construction Company. Retrieved 3 October 2026.
  6. “2009 Alberta Clipper (Wisconsin) – Hoover Construction”. Hoover Construction Company. Retrieved 3 October 2026.
  7. “Recent Projects table, 2000-2010 (archive 2011-12-07)”. U.S. Pipeline, Inc. Archived from the original on 7 December 2011. Retrieved 6 October 2026.
  8. “Canadian Line Gets U.S. Pass”. Engineering News-Record. 26 August 2009. Retrieved 6 October 2026.
  9. “Alberta Clipper pipeline construction under way in North Dakota, Minnesota”. Grand Forks Herald. 24 August 2009. Retrieved 6 October 2026.
  10. “Pipeline: Mainline (Michels Pipeline Construction)”. Michels Corporation. Archived from the original on 12 August 2014. Retrieved 3 October 2026.
  11. “20 Large-Diameter Crossings”. Trenchless Technology. 1 February 2010. Retrieved 6 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.