Bison Pipeline
From the ProvenHand pipeline wiki
Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.
Bison Pipeline is a natural gas pipeline in Wyoming, Montana and North Dakota, operated by TransCanada. Construction began in 2010 and the line entered service in 2011.[1]
| Bison Pipeline | |
|---|---|
| Also called | Bison |
| General information | |
| Project type | New build[4] |
| Status | In service[4] |
| Commodity | Natural gas[4] |
| Operator | TransCanada |
| Owner and operator | |
| States | Wyoming, Montana, North Dakota[4][5] |
| Approved | 9 April 2010[5] |
| Construction started | 14 May 2010[6] |
| In service | 14 January 2011[4] |
| FERC docket | CP09-161[5] |
| FERC pre-filing docket | PF08-23[5] |
| Contractors | |
| Technical information | |
| Length | 303 mi or 302 mi[4][5][sources disagree] |
| Pipe size | 30"[4] |
| Capacity | 477 MMcf/d (FERC project list)[4][5] |
| Cost | $609.6 million (EIA estimate; no dollar year given)[4] |
| On ProvenHand | |
| Hands listed | 0 |
Bison Pipeline is a natural gas pipeline in Wyoming, Montana and North Dakota, operated by TransCanada. Construction began in 2010 and the line entered service in 2011.[1]
Contractorsedit
| Contractor | Work | Scope | Years |
|---|---|---|---|
| Price Gregory International[3] | Spread 3 (145.2 km of 30-inch, Montana) and Spread 4 (195.0 km, North Dakota) | ||
| Price Gregory International, LLC[7] | Prime | Bison Pipeline Project Spread 3 (91 miles of 30-inch, Montana and North Dakota) and Spread 4 (118 miles of 30-inch, North Dakota) | until 1 December 2010 |
| Michels Pipeline, Inc.[8] | Pipeline construction (role not stated) | Listed on the firm's 2014 pipeline page (as Michels Pipeline Construction) among five of the largest pipeline projects it had recently worked on; role and years not stated |
Spreads
| Spread | Prime contractor | Dates |
|---|---|---|
| Spread 3[7] | Price Gregory International, LLC | until 1 December 2010 |
| Spread 4[7] | Price Gregory International, LLC | until 1 December 2010 |
Sources disagree
These sources give different values for the same fact. Each value is listed with the sources that give it.
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Bison Pipeline? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- sec.gov · a2202076z10-k.htm
- sec.gov · a2207396z10-k.htm
- rmsweldingsystems.com
- “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
- “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
- “Bison Pipeline Weekly Status Report No. 1 (revision) (CP09-161)”. Bison Pipeline LLC (filed with FERC). 21 May 2010. Retrieved 4 October 2026.
- “Price Gregory Completed Projects - Five Years (2016 list)”. Price Gregory International, LLC. 9 May 2016. Archived from the original on 9 May 2016. Retrieved 3 October 2026.
- “Pipeline: Mainline (Michels Pipeline Construction)”. Michels Corporation. Archived from the original on 12 August 2014. Retrieved 3 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.