Lonesome Creek NGL Pipeline Pjct - McKenzie is an NGL pipeline in North Dakota, operated by ONEOK Bakken Pipeline, L.L.C.. It entered service in 2015. It runs 4 miles of 8" pipe.
| Lonesome Creek NGL Pipeline Pjct - McKenzie | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Commodity | NGL[2] |
| Owner and operator | |
| State | North Dakota[1] |
| Counties | McKenzie[2] |
| Approved | 12 August 2015[2] |
| In service | 13 November 2015[3] |
| North Dakota PSC case | PU-15-137[1] |
| Contractors | |
| Technical information | |
| Length | 4 mi[2] |
| Pipe size | 8"[2] |
| Cost | $6,000,000 estimated investment (PSC siting spreadsheet)[2] |
| On ProvenHand | |
| Hands listed | 0 |
Lonesome Creek NGL Pipeline Pjct - McKenzie is an NGL pipeline in North Dakota, operated by ONEOK Bakken Pipeline, L.L.C.. It entered service in 2015. It runs 4 miles of 8" pipe.
Contractorsedit
| Contractor | Work |
|---|---|
| Jomax Construction Co., Inc.[4] | construction contractor listed among the pre-construction meeting attendees (role in the build not stated) |
Inspection
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Lonesome Creek NGL Pipeline Pjct - McKenzie? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “North Dakota Public Service Commission: case search (pipeline siting)”. North Dakota Public Service Commission. Retrieved 3 October 2026.
- “North Dakota PSC siting applications spreadsheet (siting cases 2005 to present)”. North Dakota Public Service Commission. Retrieved 3 October 2026.
- “Lonesome Creek NGL Pipeline progress report â month ending 11-30-2015, case PU-15-137, docket 41”. Filed with the North Dakota Public Service Commission. 9 December 2015. Retrieved 3 October 2026.
- “Preconstruction call minutes and landowner contact information, case PU-15-137, docket 32”. Filed with the North Dakota Public Service Commission. 25 August 2015. Retrieved 3 October 2026.
- “Permit Compliance Final Inspection Report, case PU-15-137, docket 45”. Houston Engineering, Inc. (filed with the North Dakota Public Service Commission). 19 December 2016. Retrieved 3 October 2026.