Loudon Expansion Project is a natural gas pipeline expansion in Tennessee, operated by East Tennessee Nat Gas Co. Construction began in 2016. It runs 10 miles of 12" pipe.

Loudon Expansion Project
General information
KindPipeline project[1]
Project typeExpansion[1][2]
StatusIn service[1][3]
CommodityNatural gas[1]
OperatorEast Tennessee Nat Gas Co[1]
Operator
Owner and operator
StateTennessee[1]
CountiesBradley, Loudon[4]
Approved3 March 2016[5]
Construction started24 March 2016[5]
In serviceSeptember 2016[1] or 13 September 2016[3][sources disagree]
FERC docketCP15-91[1]
Contractors
Technical information
Length10 mi[1]
Pipe size12"[1]
Capacity40 MMcf/d additional capacity (EIA)[1]
Cost$53 million (EIA estimate; no dollar year given)[1]
On ProvenHand
Hands listed0

Loudon Expansion Project is a natural gas pipeline expansion in Tennessee, operated by East Tennessee Nat Gas Co. Construction began in 2016. It runs 10 miles of 12" pipe.

Contractorsedit

ContractorWorkScope
Sunland Construction, Inc.[4]PrimeListed 2017 as contractor: 10 miles of 12-inch in Bradley and Loudon counties, TN

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
In service
  • September 2016[1]
  • 13 September 2016[3]

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Loudon Expansion Project? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  2. “FERC eLibrary docket CP15-91”. Federal Energy Regulatory Commission. 20 February 2015. Retrieved 3 October 2026.
  3. “Notice of Commencement of Service, Loudon Expansion Project (CP15-91)”. East Tennessee Natural Gas, LLC (filed with FERC). 15 September 2016. Retrieved 4 October 2026.
  4. “Ongoing Projects: Construction Underway (Pipeline News, May 2017)”. Pipeline News. May 2017. Retrieved 3 October 2026.
  5. “Request for Authorization for Commencement of Service, Loudon Expansion Project (CP15-91)”. East Tennessee Natural Gas, LLC (filed with FERC). 10 August 2016. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.