Seneca lateral
From the ProvenHand pipeline wiki
Seneca lateral is a natural gas pipeline lateral in Ohio, operated by Rockies Express Pipeline LLC. Construction began in 2013 and the line entered service in 2014. It runs 14.3 miles of 24" pipe.
| Seneca lateral | |
|---|---|
| General information | |
| Kind | Pipeline project[1] |
| Project type | Lateral[1] |
| Status | In service[1] |
| Commodity | Natural gas[1] |
| Operator | |
| Owner and operator | |
| State | Ohio[1] |
| Counties | Monroe, Noble[3] |
| Construction started | October 2013[4] |
| In service | 18 June 2014[1] |
| FERC docket | CP13-539[1] |
| Contractors | |
| Technical information | |
| Length | 14.3 mi[1][3] |
| Pipe size | 24"[1][3] |
| Capacity | 600 MMcf/d additional capacity (EIA)[1] |
| Cost | $75 million (EIA estimate; no dollar year given)[1][3] |
| On ProvenHand | |
| Hands listed | 0 |
Seneca lateral is a natural gas pipeline lateral in Ohio, operated by Rockies Express Pipeline LLC. Construction began in 2013 and the line entered service in 2014. It runs 14.3 miles of 24" pipe.
Contractorsedit
| Contractor | Work | Scope | Years |
|---|---|---|---|
| Michels Pipeline Construction, Inc.[4] | Prime | pipeline construction (mobilized October 2013) | from 21 October 2013 |
| Price Gregory International, LLC[5] | Prime | REX Seneca Lateral: 17,100 feet of 24-inch, Ohio | until 1 June 2014 |
| Price Gregory International, LLC[5] | Prime | 17,100 ft of 24-inch for Tallgrass - Rockies Express (end date Jun-14 per Price Gregory's list) | until 1 June 2014 |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Seneca lateral? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
- “FERC eLibrary docket CP13-539”. Federal Energy Regulatory Commission. 26 August 2013. Retrieved 3 October 2026.
- “Environmental Assessment Report, Rockies Express Seneca Lateral Project, advance notification of Section 311 construction (CP13-539)”. FERC. 25 September 2013. Retrieved 4 October 2026.
- “Bi-Weekly Status Report No. 1, Seneca Lateral (CP13-539)”. Rockies Express Pipeline LLC (filed with FERC). 4 November 2013. Retrieved 4 October 2026.
- “Price Gregory Completed Projects - Five Years (2016 list)”. Price Gregory International, LLC. 9 May 2016. Archived from the original on 9 May 2016. Retrieved 3 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.