Transco Regional Energy Access Expansion
From the ProvenHand pipeline wiki
Transco Regional Energy Access Expansion is a natural gas pipeline expansion in Maryland, New Jersey and Pennsylvania. Construction began in 2023 and the line entered service in 2024.
| Transco Regional Energy Access Expansion | |
|---|---|
| Also called | Regional Energy Access Project (Phase I and II)[1], Regional Energy Access Expansion Project[2] |
| General information | |
| Kind | Pipeline project[3] |
| Project type | Expansion[2][3][4] |
| Status | In service[4] |
| Commodity | Natural gas[4] |
| Operator | Williams (Transco)[3] or Transcontinental Gas Pipe Line Company, LLC[3][sources disagree] |
| Owner and operator | |
| Facility projects | |
| States | Maryland, New Jersey, Pennsylvania[1][4][5] |
| Approved | 11 January 2023[1] |
| Construction started | 16 March 2023[6] |
| In service | 12 July 2024[4] |
| Labor | Union[7] |
| FERC docket | CP21-94[1] |
| FERC pre-filing docket | PF20-3[3] |
| Contractors | |
| Technical information | |
| Length | 35.8 mi[4] or 36.1 mi[1][sources disagree] |
| Pipe size | 30", 42"[4] |
| Capacity | 829.4 MMcf/d (FERC project list)[1] or 829 MMcf/d additional capacity (EIA)[4][sources disagree] |
| On ProvenHand | |
| Hands listed | 0 |
Transco Regional Energy Access Expansion is a natural gas pipeline expansion in Maryland, New Jersey and Pennsylvania. Construction began in 2023 and the line entered service in 2024.
Contractorsedit
| Contractor | Work | Prime or sub | Scope | Spread | Years |
|---|---|---|---|---|---|
| Associated Pipe Line Contractors, Inc.[7] | Prime | 13.78 miles of 42-inch new lay steel pre-jobbed at Saylorsburg, PA (the Effort Loop in Monroe County); the union's July 2023 report says Michels and Associated picked up the Williams REA project in Pennsylvania | Effort Loop | from 1 January 2023 | |
| Hoover Construction Company[8] | Rock drilling and blasting | Under Associated Pipe Line Contractors, Inc. | Drilling and blasting for 13.6 miles of 42-inch (Effort Loop), Monroe County, PA | Effort Loop | from 17 May 2023 |
| Michels Trenchless, Inc.[9] | HDD and bore | Direct Pipe install of about 1,348 ft of 42-inch sacrificial casing under the Susquehanna River, then a 30-inch X70 pipeline with HDD pull support | |||
| Michels Pipeline, Inc.[10] | Prime | 22.3 miles of 30-inch in Luzerne County, PA, including 3,600 ft of bores and a Direct Pipe crossing under the Susquehanna River (PAH Project of the Year 2024) |
Spreads
| Spread | Prime contractor |
|---|---|
| Effort Loop[8][11] | Associated Pipe Line Contractors, Inc. |
Crossings
| Feature | Method | Contractor |
|---|---|---|
| Susquehanna River[9] | Direct pipe | Michels Trenchless, Inc. |
Sources disagree
These sources give different values for the same fact. Each value is listed with the sources that give it.
| Fact | Values given |
|---|---|
| Capacity | |
| Length | |
| Operator |
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Transco Regional Energy Access Expansion? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
- “FERC eLibrary docket CP21-94”. Federal Energy Regulatory Commission. 26 March 2021. Retrieved 3 October 2026.
- “FERC eLibrary docket PF20-3”. Federal Energy Regulatory Commission. 11 June 2020. Retrieved 3 October 2026.
- “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
- “Final Environmental Impact Statement, Regional Energy Access Expansion (CP21-94)”. FERC staff. 29 July 2022. Retrieved 4 October 2026.
- “Biweekly Construction Status Report (Mar 11-24, 2023), Regional Energy Access Expansion (CP21-94)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 29 March 2023. Retrieved 4 October 2026.
- “Blue Light Reports, July/August 2023”. Pipeliners Local Union 798. July 2023. Retrieved 6 October 2026.
- “Hoover Construction job notice: Associated Pipeline / Williams Effort Loop, Pennsylvania (dated 2023-05-17)”. Teamsters National Pipeline. 17 May 2023. Archived from the original on 28 May 2023. Retrieved 6 October 2026.
- “Regional Energy Access Expansion Project - Michels Corporation”. Michels Corporation. Retrieved 3 October 2026.
- “Pipeline expansion wins Project of the Year award”. Michels Corporation. 27 January 2025. Retrieved 6 October 2026.
- “Regional Energy Access Expansion Project, 401 Water Quality Certification Application, Section 7.0 Detailed Project Summary (Rev. 1)”. Transcontinental Gas Pipe Line Company, LLC (filed with PA DEP). March 2022. Retrieved 6 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.