Tri-County Bare Steel Project, Phase II

From the ProvenHand pipeline wiki

Tri-County Bare Steel Project, Phase II is a natural gas pipeline replacement in Pennsylvania, operated by Columbia Gas Transmission, LLC. It runs 8.3 miles of 20" pipe.

Tri-County Bare Steel Project, Phase II
General information
KindPipeline project[1]
Project typeReplacement[1]
CommodityNatural gas[2]
Owner
Operator
Part ofTri-County Bare Steel Replacement Project[3]
StatePennsylvania[1]
CountiesWashington[1][3]
FERC docketCP15-95[4]
Contractors
Technical information
Length8.3 mi[1]
Pipe size20"[1]
On ProvenHand
Hands listed0

Tri-County Bare Steel Project, Phase II is a natural gas pipeline replacement in Pennsylvania, operated by Columbia Gas Transmission, LLC. It runs 8.3 miles of 20" pipe.

Contractorsedit

ContractorWorkScope
Minnesota Limited, Inc.[1]PrimeListed 2017 as contractor: 8.3 miles of 20-inch in Washington County, PA

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Tri-County Bare Steel Project, Phase II? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “Ongoing Projects: Construction Underway (Pipeline News, September 2017)”. Pipeline News. September 2017. Retrieved 3 October 2026.
  2. “Columbia Gas Transmission, LLC application, Tri-County Bare Steel Replacement Project (CP15-95)”. Columbia Gas Transmission, LLC (filed with FERC). 20 February 2015. Retrieved 4 October 2026.
  3. “In-service approval letter, Phase 2 of the Tri-County Bare Steel Project (CP15-95)”. Federal Energy Regulatory Commission. 2 November 2017. Retrieved 4 October 2026.
  4. “Columbia Gas Transmission, LLC request for unrestricted notice to proceed on Phase I (CP15-95)”. Columbia Gas Transmission, LLC (filed with FERC). 24 March 2016. Retrieved 4 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.