Mountain Valley Pipeline is a natural gas pipeline, operated by Mountain Valley Pipeline, LLC.

Mountain Valley Pipeline
Also calledSouthgate Project[1], MVP Southgate Project[1]
General information
KindPipeline project[2]
Project typeNew build[3]
StatusIn service[3]
CommodityNatural gas[3]
Owner and operator
Facility project
StatesVA, WV[3][4] or NC, VA[2][sources disagree]
Approved13 October 2017[2] or 18 June 2020[2] or 14 July 2017[4][sources disagree]
In service11 June 2024[3] or 14 June 2024[7][sources disagree]
FERC docketCP16-10[1]
FERC pre-filing docketPF15-3[1]
West Virginia stormwater permitWVR310667[4]
Contractors
Technical information
Length301 mi[2] or 303.5 mi[3] or 73 mi[2][sources disagree]
Pipe size42"[3]
Capacity2000 MMcf/d (FERC project list)[2][3] or 375 MMcf/d (FERC project list)[2][sources disagree]
Cost$6600 million (EIA estimate; no dollar year given)[3]
On ProvenHand
Hands listed0

Mountain Valley Pipeline is a natural gas pipeline, operated by Mountain Valley Pipeline, LLC.

Contractorsedit

ContractorWorkPrime or subScopeSpreadYears
Right-Of-Way Clearing & Maintenance, Inc.[8]Clearing and reclamationSpreads A, B, C and H including tree felling; listed under Precision Pipeline/EQT (Equitable Gas)1 January 2018 – 1 January 2023
Precision Pipeline, LLC[9][10]PrimeSpreads A-D and G-I: 233.7 miles of 42-inch, West Virginia and Virginia1 January 2018 – 1 January 2024
Hoover Construction Company[11]Rock drilling and blastingPipeline rock drilling and blasting, Spread B (West Virginia)Spread B1 January 2018
Price Gregory International, LLC[10][12]PrimeSpread E6: 27 miles of 42-inch, West Virginia1 March 2018 – 30 November 2018
Hoover Construction Company[13]Rock drilling and blastingUnder Precision Pipeline, LLCDrilling and blasting on MVP Spread H, Franklin, Montgomery and Roanoke Counties, VASpread Hfrom 1 August 2023
Hoover Construction Company[14]Rock drilling and blastingUnder Precision Pipeline, LLCDrilling and blasting on MVP Spread I, Franklin and Pittsylvania Counties, VASpread Ifrom 1 August 2023
Beeghly Tree, LLC[15]Clearing and reclamationUnder Precision Pipeline, LLCSpread C (Webster and Braxton Counties, WV): 33 miles of clearing, access road clearing, tree trimming, timber mat placement and hauling, temporary stream crossingsSpread C
US Trinity Energy Services LLC[10]PrimeListed 2018-2019 as a pipeline construction contractor
Price Gregory International, LLC[16]PrimeListed through January 2023 as a pipeline construction contractor (with Precision Pipeline and US Trinity Energy Services)

Pipe mills

Spreads

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Approved
  • 13 October 2017[2]
  • 18 June 2020[2]
  • 14 July 2017[4]
Capacity
  • 2000 MMcf/d (FERC project list)[2][3]
  • 375 MMcf/d (FERC project list)[2]
In service
  • 11 June 2024[3]
  • 14 June 2024[7]
Length
States

Crew on ProvenHand

No one on ProvenHand has listed this job yet.

Did you work on Mountain Valley Pipeline? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.

Referencesedit

  1. “FERC eLibrary docket CP16-10”. Federal Energy Regulatory Commission. 23 October 2015. Retrieved 3 October 2026.
  2. “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
  3. “U.S. natural gas pipeline projects (Natural Gas Pipeline Projects)”. U.S. Energy Information Administration. Retrieved 3 October 2026.
  4. “WVDEP: Oil and Gas Construction Stormwater registrations”. West Virginia Department of Environmental Protection. Retrieved 3 October 2026.
  5. “Environmental Assessment, Mountain Valley Pipeline Amendment Project (CP21-57)”. FERC staff. 13 August 2021. Retrieved 4 October 2026.
  6. “Order Amending Certificate, Mountain Valley Pipeline, LLC (CP21-57)”. FERC (order). 8 April 2022. Retrieved 4 October 2026.
  7. “Notification of In-Service, Mountain Valley Pipeline Project (CP16-10, CP19-477, CP21-57)”. Mountain Valley Pipeline, LLC (filed with FERC). 14 June 2024. Retrieved 4 October 2026.
  8. “Projects”. Right-Of-Way Clearing & Maintenance, Inc. Retrieved 3 October 2026.
  9. “All Projects - Precision Pipeline, LLC | Infrastructure and Utility Pipeline Contractor”. Precision Pipeline, LLC. Retrieved 3 October 2026.
  10. “Ongoing Projects: Construction Underway (Pipeline News, July 2019)”. Pipeline News. July 2019. Retrieved 3 October 2026.
  11. “2018 MVP Spread B (WV) – Hoover Construction”. Hoover Construction Company. Retrieved 3 October 2026.
  12. “Price Gregory Completed Projects - Five Years (2020 list)”. Price Gregory International, LLC. June 2020. Retrieved 3 October 2026.
  13. “Hoover Construction job notice: Precision / MVP Spread H, Virginia (dated 2023-08-01)”. Teamsters National Pipeline. 1 August 2023. Archived from the original on 21 September 2023. Retrieved 6 October 2026.
  14. “Hoover Construction job notice: Precision / MVP Spread I, Virginia (dated 2023-08-01)”. Teamsters National Pipeline. 1 August 2023. Archived from the original on 30 September 2023. Retrieved 6 October 2026.
  15. “Beeghly Tree Recent Notable Projects”. Beeghly Tree, LLC. Retrieved 3 October 2026.
  16. “Pipeline News, Ongoing Projects (January 2023)”. Pipeline & Gas Journal. January 2023. Retrieved 6 October 2026.
  17. “Welspun Corp | Projects”. Welspun Corp Ltd. Retrieved 3 October 2026.
  18. “Mountain Valley Pipeline | Precision Pipeline, LLC, Signature Project”. Precision Pipeline, LLC. Retrieved 3 October 2026.

This pipeline article is a stub. You can help ProvenHand by expanding it.