Atlantic Sunrise is a natural gas pipeline. Construction began in 2017 and the line entered service in 2018.[1]
| Atlantic Sunrise | |
|---|---|
| Also called | Atlantic Sunrise Project, Central Penn Line, Transco Atlantic Sunrise |
| General information | |
| Status | In service[5] |
| Commodity | Natural gas |
| Operator | Williams (Transco)[6][7] or Transcontinental Gas Pipe Line Company, LLC[6][7][sources disagree] |
| Owner and operator | |
| Facility project | |
| State | PA or MD, NC, PA, SC, VA[8][sources disagree] |
| Approved | 3 February 2017[8] |
| Construction started | 16 March 2017[10] |
| In service | 6 October 2018[5] |
| FERC dockets | CP15-138[8], CP17-212[7], CP18-537[6] |
| FERC pre-filing docket | PF14-8[8] |
| Contractors | |
| Technical information | |
| Length | 198 mi or 196.5 mi[8][sources disagree] |
| Pipe size | 30", 42" |
| Diameters | 42 in[11] |
| Capacity | 1700 MMcf/d (FERC project list)[8] |
| On ProvenHand | |
| Hands listed | 0 |
Atlantic Sunrise is a natural gas pipeline. Construction began in 2017 and the line entered service in 2018.[1]
Contractorsedit
| Contractor | Work | Prime or sub | Scope | Spread | Years |
|---|---|---|---|---|---|
| Henkels & McCoy[2] | Primary pipeline contractor | ||||
| Latex Construction[4] | Spread 4 | ||||
| Michels[2] | Primary pipeline contractor | ||||
| Welded Construction[4] | Spread 7 | ||||
| Price Gregory International, LLC[12] | Compressor station expansion | Station 190 HP expansion (compressor station expansion), Maryland | 1 February 2017 – 31 October 2017 | ||
| The Hillis Group, LLC[13] | Clearing and reclamation | Part of 78 miles of main line restoration on Spreads 5, 6 and 7 (Columbia, Lebanon, Northumberland and Schuylkill Counties, PA), taken over from an active project | Spread 5 | 1 January 2018 – 1 January 2020 | |
| The Hillis Group, LLC[13] | Clearing and reclamation | Part of 78 miles of main line restoration on Spreads 5, 6 and 7 (Columbia, Lebanon, Northumberland and Schuylkill Counties, PA), taken over from an active project | Spread 6 | 1 January 2018 – 1 January 2020 | |
| The Hillis Group, LLC[13] | Clearing and reclamation | Part of 78 miles of main line restoration on Spreads 5, 6 and 7 (Columbia, Lebanon, Northumberland and Schuylkill Counties, PA), taken over from an active project | Spread 7 | 1 January 2018 – 1 January 2020 | |
| Aaron Enterprises, Inc.[14][15] | HDD and bore | Trenchless crossings under Amtrak and the PA Turnpike: 52-in steel sleeve, 42-in steel main, auger bore and slick bore | Spread 7 | until 1 July 2018 | |
| Latex Construction[16] | Prime | Spread 4 (listed 2017-2018) | |||
| Welded Construction, L.P.[16] | Prime | Spread 7 (listed 2017-2018) | |||
| RMS Welding Systems[17] | Mechanized welding | Under Latex Construction | Mechanized welding (MOWII system) on Spread 4 for Latex Construction: 48 km of 42-inch pipe, 18.8 and 22.5 mm wall, X-70, Pennsylvania | ||
| Latex Construction[18][19] | Prime | Spread 4: 30 miles of 42-inch new pipeline in Columbia County, PA (field office Hughesville, PA); final completion spring/summer 2019 (client Williams-Transco) | Spread 4 | until 1 January 2019 |
Spreads
| Spread | Prime contractor | Dates |
|---|---|---|
| Spread 4[16][20] | Latex Construction | until 1 January 2019 |
| Spread 5[13] | ||
| Spread 6[13] | ||
| Spread 7[13][14][16] | Welded Construction, L.P. |
Sources disagree
These sources give different values for the same fact. Each value is listed with the sources that give it.
| Fact | Values given |
|---|---|
| Length |
|
| Operator | |
| States |
|
Crew on ProvenHand
No one on ProvenHand has listed this job yet.
Did you work on Atlantic Sunrise? Add it to your work history on ProvenHand and get it confirmed by someone who was there. Sign in or join.
Referencesedit
- ogj.com
- pgjonline.com
- ferc.gov · volume-II.pdf
- s3.amazonaws.com · PLN0718_ongoing.pdf
- “Notification of placement into service, Atlantic Sunrise Project (CP15-138)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 9 October 2018. Retrieved 4 October 2026.
- “FERC eLibrary docket CP18-537”. Federal Energy Regulatory Commission. 7 August 2018. Retrieved 3 October 2026.
- “FERC eLibrary docket CP17-212”. Federal Energy Regulatory Commission. 19 April 2017. Retrieved 3 October 2026.
- “FERC: Approved Major Pipeline Projects (1997-Present)”. Federal Energy Regulatory Commission. Archived from the original on 1 July 2025. Retrieved 3 October 2026.
- “Springville Meter Station Atlantic Sunrise - The Hillis Group, LLC”. The Hillis Group, LLC. Retrieved 3 October 2026.
- “Notice of Commencement of Construction, Atlantic Sunrise Project (CP15-138)”. Transcontinental Gas Pipe Line Company, LLC (filed with FERC). 17 March 2017. Retrieved 4 October 2026.
- “Ongoing Projects: Construction Underway (Pipeline News, February 2018)”. Pipeline News. February 2018. Retrieved 3 October 2026.
- “Price Gregory Completed Projects - Five Years (2020 list)”. Price Gregory International, LLC. June 2020. Retrieved 3 October 2026.
- “Atlantic Sunrise Spreads 5, 6 & 7 - The Hillis Group, LLC”. The Hillis Group, LLC. Retrieved 3 October 2026.
- “Atlantic Sunrise Spread 7 (project profile)”. Aaron Enterprises, Inc. Retrieved 3 October 2026.
- “Project Profile: Atlantic Sunrise Spread 7”. Aaron Enterprises, Inc. Retrieved 3 October 2026.
- “Ongoing Projects: Construction Underway (Pipeline News, October 2018)”. Pipeline News. October 2018. Retrieved 3 October 2026.
- “Projects (MOWII)”. RMS Welding Systems. Retrieved 3 October 2026.
- “Current Projects | latexconstruction (November 2019 capture)”. Latex Construction Company. Archived from the original on 19 November 2019. Retrieved 6 October 2026.
- “Recently Completed Projects | latexconstruction (December 2022 capture)”. Latex Construction Company. Archived from the original on 4 December 2022. Retrieved 6 October 2026.
- “Recently Completed Projects | latexconstruction (August 2020 capture)”. Latex Construction Company. Archived from the original on 12 August 2020. Retrieved 6 October 2026.
This pipeline article is a stub. You can help ProvenHand by expanding it.