Rockford Corporation

From the ProvenHand pipeline wiki

Sources disagree on some of this page's facts. Each value is shown with its sources; see Sources disagree.

Rockford Corporation is a pipeline contractor and a pipeline owner-operator based in Heath, Texas. It is part of Primoris Services Corporation.

Rockford Corporation
Legal nameROCKFORD CORPORATION[1] or Rockford Corporation[2][sources disagree]
General information
Industry
TypePrivate[6]
StatusActive[7][8]
Parent companyPrimoris Services Corporation[9]
Successor
HeadquartersHeath, Texas[7]
RegionsUnited States (nationwide)[7][12]
Websitewww.prim.com/about/business-units/rockford[3]
PLCAMember as of 3 October 2026[3]
PHMSA operator ID32440[1]
On ProvenHand
Hands listed0

Rockford Corporation is a pipeline contractor and a pipeline owner-operator based in Heath, Texas. It is part of Primoris Services Corporation.

This company article is a stub. You can help ProvenHand by expanding it.

Projects

As contractor

ProjectWorkScopeSpreadYearsProject built
Hunter Creek Lateral[13]PrimeBuilt with Sabal Trail Spread 6 (76.6 miles of 36-inch combined, near Wildwood to Kissimmee FL)until 1 January 20172018
Okeechobee Lateral[14]PrimeListed 2018-2019 as the pipeline construction contractor2018
Okeechobee Lateral[15]Prime5.2 miles of 24-inch lateral with receiver, launcher and associated facilities in Okeechobee County, FL; listed start 3Q 2018, completion 1Q 20191 January 2018 – 1 January 20192018
SE Mkt P/L Proj[16]PrimeSpread 6 (awarded): 79.3 miles of 36-inch pipe, including 5 directional drills, 40 road bores and over 7 miles of push/pull work in Florida marshSpread 62016
Ruby Pipeline[16][17][18]PrimeSpreads 6 and 7: 127 miles of 42-inch, Vya NV to Malin OR1 June 2010 – 1 January 20112010–2011
Gulf Crossing Pipeline (ferc:CP07-398)[19][20]PrimeGulf Crossing Expansion Project: 54 miles of 42-inch in East Texas into Louisiana; wetland constructionuntil 1 October 20082009
Lodi Gas Storage System Phase 2 Project[21]Prime4,800 feet of 12-inch pipe to three well pads, two compressor stations (6,300 HP combined); adds 12 Bcf working gas storage capacityuntil 1 May 20092009
Lodi Gas Storage System Phase 2 Project[22]PrimePhase 2: 4,800 ft of 12-inch to three well pads, hook-up of 8 well heads, two compressors totaling 6,300 HP with building, skids and piping (for Lodi Gas Storage, LLC)until 1 May 20092009
Phoenix Expansion-Phoenix P/L / San Juan '08 Exp[19][23][24]Prime150 miles of 36-inch from north of Phoenix to Casa Grande AZuntil 1 December 20082009
El Paso to Phoenix Expansion Project[19][23]Prime128.4 miles of 16-inch and 9.6 miles of 12-inch pipe in TX, NM and AZuntil 1 December 20082007
East Line Expansion Project[25]Prime235 miles of 16-inch and 12-inch pipe in TX, NM and AZ, with survey, x-ray, GPS as-builts and hydro testinguntil 1 June 20062006
Lodi (Kirby Hills) Lateral[26][27]PrimeLodi Gas Storage Kirby Hill facility: 6 miles of 16-inch linked to PG&E's 400 line, plus a compressor/injection plantuntil 1 November 20072006
Northwest Pipeline Capacity Replacement Project[25]PrimeFt. Lewis Spread (22.5 miles of 36-inch, near Tacoma WA) and Snohomish Spread (11.8 miles of 36-inch, near Redmond WA)until 1 October 20062006
Concord Tank Farm and Terminal Modification Project[22]PrimeTerminal upgrade in Concord, CA for a new larger-capacity 20-inch pipeline to Sacramento: retaining walls, launcher and receiver, tank lines, surge header and tank, new dike, pumps and prover, tie-ins, with the terminal kept in operationuntil 1 December 20042004
Wild Goose Lateral[23][27]PrimeWild Goose Project: 25 miles of 30-inch, 0.438 wall, X-70 pipe (listed under 2002-2005 projects)until 1 September 20032003
PG&E Redwood Path[23][27]PrimeRedwood Path 42-inch Expansion: filled two skips totaling 14 miles in northern California (listed under 2002-2005 projects)until 1 August 20022002
Atlantic Coast Pipeline Project[28]PrimeListed 2018-2019 as a pipeline construction contractor
Atlantic Coast Pipeline Project[29]Prime25% partner in the Spring Ridge Constructors, LLC joint venture that held the construction contract; about $680 million of the contract carried in Primoris backlog; Rockford construction work expected to begin in 2018
Bluestone Loop 3C[30]PrimeListed 2017 as contractor: 4.5 miles of 24-inch looping near Binghamton, NY
Bluestone Loop 3C[31]Prime4.5 miles of 24-inch looping near Binghamton, NY for DTE Energy (entry dated 2/17, completion 2017)until 1 January 2017
Ehrenberg Compressor Station Project[19]PrimeChanged out two compressors and installed two Solar Taurus 60 7700 HP units with piping and skids (client: Solar Turbines/TransCanada)until 1 June 2008
Ehrenberg Compressor Station Project[22]PrimeChange-out of two Rolls Royce compressors for two Solar Taurus 60 units with associated piping and skids at Ehrenberg, AZ (for TransCanada, with Solar Turbines)until 1 June 2008
Katy Pipeline Project[23][26][27]Prime54 miles of 42-inch (2007 page: Groveton to Texoma); one HDD, 24 road bores, 27 private road crossings, one railroad crossinguntil 1 May 2007
Laser Northeast Gathering System Project[32]Prime14.8 miles of 16-inch in Susquehanna County PA; 26 directional drills and 10 road boresuntil 1 October 2011
M2E3 Project[33]PrimeSegments 4 and 7: 134 miles of 36-inch (Burnet and Houston TX); 26 HDDs, 188 bores, 15 mainline valvesuntil 1 January 2020
Ohio Valley Midstream 12-inch Ethane Project[34]Prime50 miles of 12-inch ethane pipeline near West Alexander, PAuntil 1 January 2014
Rancho Pipeline Expansion Project[16][35]Prime86 miles of 36-inch near Houston TX; 18 HDDs, 14,600 feet of bores, 62,000 timber matsuntil 1 January 2015
Ryckman Creek Ruby Pipeline Lateral Project[27]Prime5.2 miles of 16-inch and 2.1 miles of 8-inch pipe near Evanston WYuntil 1 January 2012
Sherwood to Majorsville Project[16]Prime28.2 miles of 12-inch in WV (client MarkWest)until 1 January 2015
Sherwood to Majorsville Project[34]Prime28.2 miles of 12-inch in WV and PA (for MarkWest Energy)until 1 January 2014
Strope to Wheeler Project[27]Prime8 miles of 16-inch and 2 miles of 20-inch pipe in Bradford County PA (for Talisman Energy)until 1 January 2013
Tichenal to Middlepoint[4][16]Primeuntil 1 January 2013
Wild Goose Storage Compressor Station Expansion Project[21]Prime4 miles of 24-inch pipe, well pad piping and two new CAT 3612 compressors (for Niska Gas Storage)until 1 January 2009
Zinnia Loop Project[34]Prime6.5 miles of 12-inch near Clarksburg, WV (listed as under construction on the 2014 projects page)

Spreads

Spreads this company built as the prime contractor.

Sources disagree

These sources give different values for the same fact. Each value is listed with the sources that give it.

FactValues given
Legal name
  • ROCKFORD CORPORATION[1]
  • Rockford Corporation[2]

References

  1. “PHMSA annual report data: annual gas transmission gathering 2001 2009”. Pipeline and Hazardous Materials Safety Administration. Archived from the original on 8 May 2026. Retrieved 3 October 2026.
  2. “Primoris Services Corporation Form 10-K fiscal 2014, Exhibit 21.1 subsidiaries”. Primoris Services Corporation (filed with the SEC). 16 March 2015. Retrieved 6 October 2026.
  3. “PLCA Member Directory”. Pipe Line Contractors Association. Retrieved 3 October 2026.
  4. “Tichenal to Middlepoint in Clarksburg, WV – Pedero”. Pedero Pipe Support Systems USA. Archived from the original on 3 March 2017. Retrieved 3 October 2026.
  5. “Florida Southeast Connector Pipeline Project (Rockford project sheet)”. Primoris Services Corporation. Retrieved 3 October 2026.
  6. “Primoris Services Corporation Form 10-K for fiscal 2012”. Primoris Services Corporation (filed with the SEC). 7 March 2013. Retrieved 6 October 2026.
  7. “Rockford - Primoris”. Primoris Services Corporation. Retrieved 3 October 2026.
  8. “Primoris Services Corporation Form 10-K fiscal 2025, Exhibit 21.1 subsidiaries”. Primoris Services Corporation (filed with the SEC). 24 February 2026. Retrieved 6 October 2026.
  9. “Primoris Services Corporation, annual report on Form 10-K for fiscal 2013”. Primoris Services Corporation (filed with the SEC). 3 March 2014. Retrieved 3 October 2026.
  10. “Form 8-K: completion of merger with Rockford Holdings Corporation”. Primoris Services Corporation. 12 November 2010. Retrieved 3 October 2026.
  11. “ABOUT US”. Rockford Corporation. Archived from the original on 6 November 2016. Retrieved 3 October 2026.
  12. “Rockford Corporation :: Oil & Gas Pipeline Construction”. Rockford Corporation. Archived from the original on 14 October 2010. Retrieved 6 October 2026.
  13. “Sabal Trail Spread 6 (Rockford project sheet)”. Primoris Services Corporation. Retrieved 3 October 2026.
  14. “Ongoing Projects: Construction Underway (Pipeline News, February 2019)”. Pipeline News. February 2019. Retrieved 3 October 2026.
  15. “Ongoing Projects: Construction Underway (Pipeline News, June 2018)”. Pipeline News. June 2018. Retrieved 3 October 2026.
  16. “PROJECTS”. Rockford Corporation. Archived from the original on 6 November 2016. Retrieved 3 October 2026.
  17. “Ruby Project (Rockford project sheet)”. Primoris Services Corporation. Retrieved 3 October 2026.
  18. “Primoris Services Corporation to acquire Rockford Corporation (press release, Form 8-K exhibit 99.1)”. Primoris Services Corporation. 9 November 2010. Retrieved 3 October 2026.
  19. “2008 Projects”. Rockford Corporation. Archived from the original on 7 December 2015. Retrieved 3 October 2026.
  20. “Gulf Crossing Expansion » Rockford Corporation”. Rockford Corporation. Archived from the original on 11 May 2009. Retrieved 3 October 2026.
  21. “2009 Projects”. Rockford Corporation. Archived from the original on 7 December 2015. Retrieved 3 October 2026.
  22. “Rockford Corporation :: Compressor Station & Storage Work”. Rockford Corporation. Archived from the original on 14 October 2010. Retrieved 6 October 2026.
  23. “Rockford Corporation :: Company References”. Rockford Corporation. Archived from the original on 14 October 2010. Retrieved 3 October 2026.
  24. “Rockford Corporation past projects (2008 projects)”. Rockford Corporation (archived company page). Archived from the original on 14 October 2010. Retrieved 4 October 2026.
  25. “2006 Projects”. Rockford Corporation. Archived from the original on 7 December 2015. Retrieved 3 October 2026.
  26. “2007 Projects”. Rockford Corporation. Archived from the original on 7 December 2015. Retrieved 3 October 2026.
  27. “Past Projects”. Rockford Corporation. Archived from the original on 10 October 2015. Retrieved 3 October 2026.
  28. “Ongoing Projects: Construction Underway (Pipeline News, August 2019)”. Pipeline News. August 2019. Retrieved 3 October 2026.
  29. “Primoris Services Corporation Form 10-K for fiscal 2016”. Primoris Services Corporation (filed with the SEC). 28 February 2017. Retrieved 6 October 2026.
  30. “Ongoing Projects: Construction Underway (Pipeline News, May 2017)”. Pipeline News. May 2017. Retrieved 3 October 2026.
  31. “Ongoing Projects: Construction Underway (Pipeline News, March 2017)”. Pipeline News. March 2017. Retrieved 3 October 2026.
  32. “2011 Projects”. Rockford Corporation. Archived from the original on 7 December 2015. Retrieved 3 October 2026.
  33. “M2E3 Project (Rockford project sheet)”. Primoris Services Corporation. Retrieved 3 October 2026.
  34. “2014 Projects”. Rockford Corporation. Archived from the original on 7 December 2015. Retrieved 6 October 2026.
  35. “Rancho Pipeline Project (Rockford project sheet)”. Primoris Services Corporation. Retrieved 3 October 2026.